Access Point Improvement Project

SOL #: 12441926Q0015Combined Synopsis/Solicitation

Overview

Buyer

Agriculture
Forest Service
USDA FOREST SERVICE-SPOC EAST
Washington, DC, 202500001, United States

Place of Performance

San Dimas, CA

NAICS

All Other Specialty Trade Contractors (238990)

PSC

Repair Or Alteration Of Other Non Building Facilities (Z2PZ)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Jan 15, 2026
2
Last Updated
Jan 30, 2026
3
Submission Deadline
Feb 5, 2026, 10:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The USDA Forest Service is soliciting quotations for the Access Point Improvement Project (Solicitation 12441926Q0015) at the USFS National Technology and Development Program campus in San Dimas, CA. This project involves constructing a new secured, ADA-compliant access point, including demolition, driveway construction, and installation of new fencing and gates. This acquisition is a Total Small Business Set-Aside.

Scope of Work

The project's objective is to enhance safe, ADA-compliant, and secure ingress/egress for campus operations, emergency response, and perimeter security. Key activities include:

  • Demolition of existing sidewalks, curbs, gutters, and fencing.
  • Site preparation, clearing, and grading.
  • Construction of a new commercial driveway approach, approximately 30-ft wide, with ADA-compliant truncated domes.
  • Installation of approximately 143-160 linear feet of 6-ft tall chain link fencing with 3-string barbwire.
  • Installation of two chain link swinging gates for a 30-ft clear opening, also with barbwire.
  • Obtaining necessary permits, including an Encroachment Permit from the City of San Dimas.
  • Traffic control, surveying, and materials/compaction testing.
  • Final cleanup. The work will be performed at 444 E. Bonita Ave, San Dimas, CA, including portions within the City of San Dimas right-of-way. Visual details are provided in Attachment 4 (SOW Exhibits).

Contract Details

  • Contract Type: Firm Fixed Price (RFQ)
  • Anticipated Award: One award
  • Period of Performance: To be completed within 90 calendar days after Notice to Proceed (NTP), with work commencing within 14 days of NTP.
  • Set-Aside: Total Small Business Set-Aside (FAR 19.5)
  • NAICS Code: 238990 (Repair Or Alteration Of Other Non Building Facilities)
  • Small Business Size Standard: $19 million

Submission & Evaluation

  • Questions Due: January 29, 2025, 3:00 PM Eastern Time.
  • Quotes Due: February 5, 2025, 3:00 PM Eastern Time.
  • Submission Method: Email to Arthur Courtney (arthur.courtney@usda.gov).
  • Evaluation Criteria: Lowest Price Technically Acceptable (LPTA). Technical acceptability will be rated "acceptable" or "unacceptable," and Past Performance will be rated "Acceptable" or "Neutral." Offerors must provide an explanation of their ability to perform.

Special Requirements & Notes

  • A pre-bid site visit is strongly encouraged. Contact Kenneth Bailey (kenneth.bailey@usda.gov, 626-422-7840) to arrange.
  • Contractor must comply with City of San Dimas codes, MUTCD, and USFS requirements.
  • Prevailing wage rates for Los Angeles County (GDN CA20260022) apply, as detailed in Attachment 7.
  • Government-furnished items include electricity and water.
  • Construction hours are Monday-Friday, 7:30 am to 4:30 pm, excluding Federal Holidays.
  • Contractor must provide two weeks' advance written notification to affected residents/businesses.
  • Key personnel requirements include Project Manager, Estimator, Site Superintendent, Foreman, and Quality Control Inspector.
  • Deliverables include Project Plan, Construction Schedule, Safety Plan, QC Plan, and As-Built Drawings.

People

Points of Contact

Arthur CourtneyPRIMARY

Files

Files

No files attached to this opportunity

Versions

Version 2
Combined Synopsis/Solicitation
Posted: Jan 30, 2026
View
Version 1Viewing
Combined Synopsis/Solicitation
Posted: Jan 15, 2026
Access Point Improvement Project | GovScope