C-5 Avionics Regulated Transformer Rectifier Unit (RTRU) 400 AMP
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Defense Logistics Agency (DLA) Aviation at Warner Robins, GA, intends to award a sole source Requirements Indefinite Delivery Contract (IDC) for the C-5 Avionics Regulated Transformer Rectifier Unit (RTRU) 400 AMP (NSN: 6120-01-524-9044UC, P/N: 716340-1). The Government plans to solicit and negotiate exclusively with GE Aviation (CAGE 19623), citing FAR 6.302-1 due to not owning the data rights. Proposals are due by July 10, 2026.
Scope of Work
This acquisition seeks a production first article, flight-ready RTRU 400 AMP for the C-5 aircraft, providing regulated +28 VDC at 400A. The contractor will manufacture, inspect, test, and deliver RTRU assets conforming to approved designs, addressing Diminishing Manufacturing Sources and Material Shortages (DMSMS) and obsolescence issues. The units are essential for C-5 Avionics until the aircraft's retirement in 2050.
Contract Details
- Contract Type: Requirements Indefinite Delivery Contract (IDC)
- Set-Aside: Sole Source (GE Aviation)
- Period of Performance: One (1) basic year plus four (4) one-year options, totaling five (5) years.
- Estimated Quantities: One (1) production first article unit (due within 3 months of contract award) and a Best Estimated Quantity (BEQ) of 58 production units.
- Delivery: Production units requested 38 weeks ARO.
- Place of Performance: Contractor's facilities, with potential flight/integration testing at a USAF installation.
- Response Date: July 10, 2026
Key Requirements
- Technical: Deliver a Form, Fit, Function, and Interface (F3I) production flight-ready RTRU 400 AMP. All units must pass Formal Qualification per Source Control Drawing (SCD) 4B99005 and meet specifications LG03ER0144 and LG03ER0124.
- Data & Plans: Submission of an Item Unique Identification (IUID) Marking Plan, IUID Marking Activity Validation and Verification Report, and a Counterfeit Prevention Plan (CPP) is required.
- Compliance: Adherence to SAE AS5553 for counterfeit electronics prevention, AFMC Form 158 for packaging, MIL-STD-2073-1 and MIL-STD-129 for marking, and DD Form 1653 for transportation. Contractors must also develop a Supply Chain Risk Management (SCRM) plan and comply with security and cybersecurity best practices.
- First Article: One (1) production first article flight-ready unit is required within 3 months of contract award for validation.
Submission & Contact
Proposals must be submitted by the deadline. For inquiries, contact Victor Henderson (victor.henderson.2@us.af.mil) or Erika Bell (erika.bell.2@us.af.mil).