CNF-CON FSLM-Park Falls Parking Lot Paving
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of Agriculture (USDA) Forest Service has issued a combined synopsis/solicitation for the Park Falls Parking Lot Paving project in Park Falls, WI. This requirement involves comprehensive paving and site improvements at the Forest Service office. Quotations are due by February 23, 2026, at 5:00 PM Eastern.
Scope of Work
The contractor will provide all labor, materials, and equipment for site improvements as detailed in the technical specifications and engineering plans. Key tasks include:
- Paving & Surfacing: Asphaltic surface application, aggregate base installation, fog sealing, and paved ditch construction.
- Site Infrastructure: Construction of ADA-compliant ramps, sidewalks, and drainage improvements.
- Maintenance & Restoration: Soil erosion and pollution control, seeding, and pavement marking.
- Traffic Management: Implementation of traffic control plans and temporary parking lot closures during construction.
Contract & Timeline
- Type: Firm Fixed-Price (FFP) Purchase Order
- Duration: Completion required within 90 days after receipt of the Notice to Proceed (NTP).
- Set-Aside: Total Small Business Set-Aside
- Response Due: February 23, 2026
- NAICS Code: 237310 (Construction of Highways, Roads, Streets, Bridges, and Railways)
Evaluation
Award will be made to the responsible offeror providing the Lowest Price among quotes deemed technically acceptable. Acceptability is based on compliance with solicitation instructions, while responsibility includes assessments of past performance and financial health.
Additional Notes
This project is subject to Davis-Bacon Act wage determinations (WI20260010). Technical specifications adopt the FP-14 standards for National Forest System Road construction with significant modifications to sections 101 through 625. Offerors must submit pricing for all items listed in the Schedule of Items to be considered responsive.