Control Tower Chamber Equipment Painting, Colebrook River Lake, Colebrook, CT
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Army, New England District, is soliciting quotes for Control Tower Chamber Equipment Painting at Colebrook River Lake, Colebrook, CT. This Total Small Business Set-Aside opportunity involves preparation and painting of various mechanical equipment within the gate chamber. The estimated magnitude of construction is between $100,000 and $250,000. Quotes are due by April 27, 2026, at 5:00 PM Eastern.
Scope of Work
The project requires preparation and painting of steel components in the gate chamber, including bonnets, hydraulic piping, cylinders, sump pump plumbing (excluding pumps), conduit pressure balancing pipe, vertical float well pipe, air shafts, and the entire spiral staircase. Preparation involves solvent cleaning and mechanical removal of loose paint/rust; dry abrasive blasting or water blasting of sound paint is prohibited. Painting requires an epoxy primer/sealer on corroded areas, followed by an overcoat matching existing paint color. The work assumes lead-containing paint and is considered a permit-required confined space. The contractor must adhere to strict worker health, safety, and environmental protection measures. The dam tower crane is unavailable, but the 5-ton winch hoist in the control tower is available.
Contract Details
This is a Firm Fixed Price Request for Quotation (RFQ). Work must commence within 30 calendar days and be completed within 120 calendar days after the Notice to Proceed. Insurance requirements include Workmen's Compensation, Employers' Liability, General Liability, and Automobile Liability.
Submission & Evaluation
Quotes are due by April 27, 2026, at 5:00 PM Eastern, and must be submitted via email to the Contract Specialist. A mandatory "Solicitation Survey" form must be completed and submitted with the quote, detailing company information, experience, personnel, and past performance. Evaluation will consider technical capability, price, and past performance. Vendors must have an active SAM.gov registration at the time of submission to be considered; non-registered vendors will be rejected. Site visits are highly recommended.
Key Documents & Amendments
Amendment 0001 was issued to post the site visit attendee list, confirming the closing date remains April 27, 2026. The Solicitation Survey (Form/Attachment) is a critical component for bidder evaluation. The Statement of Work (SOW) provides detailed requirements for the painting project, including specific submittals like Accident Prevention Plan, Site Safety and Health Plan, and Confined Space Plan.
Contact Information