Eglin Paving IDIQ Ceiling Increase
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Air Force (DEPT OF DEFENSE) has issued a Justification for a ceiling increase and ordering period extension for the Eglin Paving IDIQ contract (FA2823-20-D-0003) at Eglin Air Force Base, FL. This posting serves as a public notification for a modification that was previously implemented, with the contract having since ended. The original justification was not publicly posted due to a system error.
Scope of Change
This Justification and Approval (J&A) supports a modification to the existing paving services contract. Key changes include:
- Ceiling Increase: The contract ceiling was increased by $1,000,000.00, raising the total from $49,000,000.00 to $50,000,000.00.
- Ordering Period Extension: The ordering period was extended by 22 days, from September 8, 2025, to September 30, 2025.
The justification for these actions was based on an "Unusual and Compelling Urgency" due to critical safety hazards at the Navy Explosive Ordnance Disposal (EOD) school and degradation of existing paved areas. Timely repairs were required to prevent further damage and ensure operational readiness. Full and open competition was deemed impractical due to the estimated 180-200 days required for a new solicitation process, which would have caused unacceptable delays.
Contract & Timeline
- Type: Justification for an existing IDIQ contract modification (FA2823-20-D-0003).
- Product/Service Code: Z2LB (Repair Or Alteration Of Highways/Roads/Streets/Bridges/Railways).
- Set-Aside: None specified.
- Published: February 24, 2026.
- Contract Status: The contract has since ended.
Additional Notes
This modification was not a solicitation and did not require new proposal submissions. This public notice is to ensure compliance with public notification requirements for the previously executed contract modification.