F--WA-FWS SPRING CRK ASBESTOS ABATEMENT
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The U.S. Fish and Wildlife Service (FWS) is soliciting proposals for Asbestos Abatement services at the Spring Creek National Fish Hatchery (NFH) in Underwood, Washington. This Total Small Business Set-Aside opportunity involves the removal, disposal, and replacement of asbestos ceiling tiles in the Incubation Building's water laboratory. The solicitation, 140FC326Q0001, has been amended twice, with the latest amendment extending the proposal deadline. Quotes are due by February 5, 2026, at 5:00 PM PST.
Scope of Work
The contractor will be responsible for the complete containment, removal, and disposal of approximately 168 square feet of overhead asbestos ceiling tiles in the Incubation Building's water laboratory. This includes preparing the work area by sealing it off, setting up a negative pressure system, transporting asbestos waste to a licensed landfill, and performing post-removal monitoring. Following abatement, new ceiling tiles must be installed. An Asbestos Testing Report (A06) identifies specific asbestos-containing materials, including brown ceiling tile mastic, and notes the substrate above the ceiling tiles is drywall.
Contract Details
- Contract Type: Firm Fixed Price Construction
- Estimated Value: Less than $25,000
- Set-Aside: Total Small Business Set-Aside (FAR 19.5)
- Period of Performance: May 1, 2026, to July 31, 2026. Work must be completed within this window, starting within 15 calendar days of receiving notice to proceed and finishing within 92 calendar days.
- Place of Performance: Spring Creek NFH, 61552 State Road 14, Underwood, WA 98651.
Key Requirements & Information
Contractors must demonstrate experience in asbestos abatement and removal. A site visit was previously encouraged (January 6, 2026). Bidders must supply all tools, materials, and equipment, including a dumpster for proper asbestos disposal. The project is subject to Davis-Bacon Act wage rates for building construction in Skamania County, Washington, as detailed in General Decision Number WA20250120. The provided Asbestos Testing Report (A06) is crucial for project planning, safety protocols, and cost estimation, as it also identifies lead-based paint in interior samples.
Submission & Evaluation
- Proposal Due: February 5, 2026, by 5:00 PM PST.
- Submission Method: Quotes must be submitted via email to Cindy Salazar (cindy_salazar@fws.gov).
- Evaluation Factors: Technical Capability, Past Performance, Work Window, and Price.
- Award Basis: Best value to the Government.
- Acknowledgement: Bidders must acknowledge receipt of all amendments. The Bid Schedule (B03) must be completed accurately for pricing.
Amendments
This solicitation has been modified by Amendment 0001 (effective 01/26/2026) and Amendment 0002 (posted 02/03/2026). These amendments extended the response deadline, clarified submission instructions, and provided the Asbestos Testing Report.