J062--Replace street light pole concrete bases.

SOL #: 36C26326Q0712Combined Synopsis/Solicitation

Overview

Buyer

Veterans Affairs
Veterans Affairs, Department Of
NETWORK CONTRACT OFFICE 23 (36C263)
Saint Paul, MN, 55101, United States

Place of Performance

St. Cloud, MN

NAICS

Electrical Contractors and Other Wiring Installation Contractors (238210)

PSC

Maintenance, Repair And Rebuilding Of Equipment: Lighting Fixtures And Lamps (J062)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
May 18, 2026
2
Last Updated
May 18, 2026
3
Submission Deadline
Jun 2, 2026, 10:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of Veterans Affairs (VA), specifically the NETWORK CONTRACT OFFICE 23 (36C263), is soliciting quotes for the replacement of street light pole concrete bases at the St. Cloud VA Health Care System in St. Cloud, MN. This is a Total Small Business Set-Aside opportunity. Quotes are due by June 2, 2026, at 5:00 PM CDT.

Scope of Work

This Request for Quote (RFQ) requires a contractor to provide all labor, materials, equipment, and disposal for replacing existing streetlight pole concrete bases. Key deliverables include:

  • Replacement of twenty-six (26) existing 30-foot high streetlight pole concrete bases with new, higher concrete bases.
  • Replacement of approximately 7,600 feet of pole feeds between light poles.
  • Replacement of light pole head feeds, fuse holders, and fuses at 26 locations.
  • Paint repair for approximately thirty-one (31) light poles, including rust repair and touch-up.
  • Work involves removing existing bases and wiring, isolating circuits, installing new bases and wiring, re-installing light poles, and performing paint touch-ups.
  • Specific materials include copper cables (no aluminum), concrete bases, 12-3 gauge SOOW wire, #8 AWG THWN cable, fuses, grounding rods, primer, and paint.
  • The street light circuit must remain operational each night. Detailed campus plan drawings (LPB-01, LPB-02) and pole base replacement details (DET 1) are provided.

Contract & Timeline

  • Contract Type: Combined Synopsis/Solicitation (RFQ), implied Fixed-Price for commercial items.
  • Period of Performance: 90 calendar days from Notice to Proceed (NTP), comprising a 20-day administrative period and 70 days of field work.
  • Set-Aside: Total Small Business Set-Aside (FAR 19.5).
  • NAICS Code: 238210 (Electrical Contractors and Other Wiring Installation Contractors) with a $19 Million SBA Size Standard.
  • Published Date: May 18, 2026.
  • Site Visit: May 26, 2026, at 10:00 AM CDT at the Facilities Management Office, Building 3, Second Floor, St. Cloud VA Health Care System.
  • Site Visit Attendance Due: May 22, 2026, by 10:00 AM CDT.
  • Questions Due: May 27, 2026, by 12:00 PM CDT.
  • Quotes Due: June 2, 2026, by 5:00 PM CDT.

Submission & Evaluation

  • Submission: Quotes must be emailed to Safa Shleiwet at safa.shleiwet@va.gov. Offerors are responsible for ensuring their entire quote is received by the deadline.
  • Eligibility: Offerors must be registered and current in the System for Award Management (SAM).
  • Evaluation Factors (descending order of importance):
    1. Technical Approach
    2. Past Performance
    3. Price
  • The Government reserves the right to award to the most advantageous offer, considering price and other factors.

Additional Notes

A Wage Determination document is included, outlining minimum hourly wage rates and fringe benefits for various occupations in Benton and Stearns Counties, MN, under the Service Contract Act. Bidders must ensure their proposed labor costs comply with these mandated rates. Offerors are responsible for all quotation preparation costs and must comply with all applicable Federal, State, Local laws, OSHA, NFPA, and VA requirements.

People

Points of Contact

Safa ShleiwetContract SpecialistPRIMARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 2Viewing
Combined Synopsis/Solicitation
Posted: May 18, 2026
Version 1
Combined Synopsis/Solicitation
Posted: May 18, 2026
View