JOFOC for SSC Tornado Resiliency - Generator Replacement for Test Complex
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The National Aeronautics and Space Administration (NASA) Stennis Space Center has posted a Justification for Other Than Full and Open Competition (JOFOC) for the SSC Tornado Resiliency - Generator Replacement for Test Complex project (80SSC026F0007). This JOFOC outlines the rationale for a sole-source Task Order award to Mississippi Power Co (MPC) against GSA Areawide Public Utility Contract 47PA0425D0027.
Scope of Work
The project involves the major restoration and replacement of generators at SSC's Test Complex, specifically at B-4400. Key requirements include:
- Replacement of four existing 1.5MW, 4160V generators with new 480V generators capable of delivering a maximum of 3.5MW emergency power (2x1750kW configuration).
- Performing a load study for generator sizing.
- Providing necessary equipment: 15kV breaker, 480V step-up transformers, NEMA 3R Low Voltage switchgear/equipment, and relays.
- Integrating new generators with day-tanks, existing B-4400 diesel storage tanks, and new piping/transfer pumps.
- Including provisions for connecting a spare/portable generator.
- Connecting new generators to the site Emergency Management and Control System (EMCS) and B-4400 Control room for monitoring.
- Ensuring new generators can synchronize with the utility power grid.
- Replacing existing knife-blade switches on Circuits 11 and 21 with new Gang-Operated Air Break (GOAB) switches.
- Replacing sand fuses feeding B-4400 480VAC transformers.
Contract & Timeline
- Type: Justification for Other Than Full and Open Competition (JOFOC) for a sole-source Task Order.
- Contract Vehicle: GSA Areawide Public Utility Contract 47PA0425D0027.
- Estimated Completion: 30 months.
- Published Date: May 19, 2026.
Eligibility / Set-Aside
This acquisition is justified for other than full and open competition, citing 10 U.S.C. 3204(a)(1) and FAR 6.103-1. The rationale is that Mississippi Power Co (MPC) is the only entity with the legal authority and technical control over its distribution system required for secure and reliable integration of the new generators.
Evaluation
This document is a justification for a sole-source award, not a solicitation for proposals. The contracting officer will perform a proposal analysis to ensure the final price is fair and reasonable.
Additional Notes
The existing generators have been in service for 56 years and are considered outdated and unreliable. This project is ancillary to the electric service already provided by MPC. NASA will continue to examine the market for future alternative solutions or new sources.