LOLO NATIONAL FOREST - Upper West Fork Fish Creek Trail Bridge Replacement
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
PROJECT DESCRIPTION: The intent of the contract is to remove and replace an existing trail bridge and substructure elements on Trail 101, milepost 3.1 on the Ninemile Ranger District, Lolo National Forest, within the Great Burn ProposedWilderness. The structure is located in Section 19, Township 13 North, Range 25 West, Mineral County, Montana. The contractor is to furnish the replacement trail bridge structure and substructure.
This project includes, but is not limited to, removing and disposing of the existing trail bridge and substructure elements, structural excavation and installation of foundation components, furnishing, loading, hauling and erecting the bridge, adjustment of adjacent trail grades to match design plans, and all other incidental items necessary to complete the work according to the contract. This project is located within a proposed wilderness area therefore a list of Resource Protection Measures and Restricted Equipment is required for this project
PROJECT LOCATION: The project can be accessed by traveling 37 miles west of Missoula on Interstate 90. Take the Fish Creek Exit #66. Follow Fish Creek Road #343 south to West Fork Fish Creek Road #7750. Follow Road #7750 to the end at Clearwater
Crossing Campground. The project is located on Trail 101 at milepost 3.1.
PERIOD OF PERFORMANCE: All work items must be completed by October 15, 2026. In-stream work is only permitted from July 15th to August 15th.
MAGNITUDE OF CONSTRUCTION (per FAR 36.204(b)): Between $250,000 and $500,000.
BONDING: All offerors will be required to provide a Bid Bond (20%) with their proposal submission. Performance and Payment Bonds (100% each) will be required of the successful awardee.