Mouth of the Columbia River (MCR) North Jetty Rehab Project Phase 2

SOL #: PAN25P04540Sources Sought

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W071 ENDIST PORTLAND
PORTLAND, OR, 97204-3495, United States

Place of Performance

Ilwaco, WA

NAICS

Other Heavy and Civil Engineering Construction (237990)

PSC

Repair Or Alteration Of Other Conservation And Development Facilities (Z2KZ)

Set Aside

No set aside specified

Timeline

1
Posted
Feb 25, 2026
2
Last Updated
Mar 2, 2026
3
Response Deadline
Mar 26, 2026, 10:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The U.S. Army Corps of Engineers (USACE), Portland District, is conducting a Sources Sought for the Mouth of the Columbia River (MCR) North Jetty Rehabilitation Project Phase 2 near Ilwaco, WA. This is for market research to identify interested and capable firms for future heavy civil engineering construction. The project involves significant jetty repair work. Responses are due by 3:00 pm PDT on March 26, 2026.

Project Scope

This project focuses on rehabilitating the MCR North Jetty, which is critical for deep-draft navigation. Mandatory work includes toe, side slope, and crest repair along approximately 900 feet of the jetty trunk, primarily on the ocean side. This involves reconstructing sections to a design crest width of 30 feet and a crest elevation of +24.5 feet NAVD88, requiring an estimated 11,100 cubic yards of stone (20-40 tons each, min. 185 pcf). Construction methods include standard repair and reconstruction, which involves recycling existing armor and placing new stone. A jetty crest haul road and staging area must be developed.

Optional work includes repairs to an additional 2,750 feet of jetty trunk, requiring an estimated 10,900 cubic yards of stone (15-40 tons each, min. 175 pcf).

Construction is expected to occur in calendar years 2027 and potentially 2028, primarily between November and April, outside of the favorable work season due to marine conditions.

Contract Details & Timeline

  • Type: Sources Sought (for market research only, not a solicitation).
  • NAICS: 237990, Other Heavy and Civil Engineering Construction (Size Standard: $45.0 million).
  • Anticipated Contract Type: One (1) Firm Fixed-Price contract.
  • Acquisition Strategy: Not yet determined, but maximum Small Business participation is sought at prime and subcontracting levels.
  • Anticipated Source Selection: Invitation for Bid.
  • Anticipated Schedule: Advertise Oct 2026, Award Dec 2026, Construction completion by end of 2028.
  • Response Due: March 26, 2026, by 3:00 pm PDT.
  • Published: February 25, 2026.

Set-Aside & Participation

This market research seeks responses from Large and Small Businesses, including Small Business, Small Disadvantaged Businesses (8(a)), HUBZone, Woman Owned Small Business (WOSB), Economically Disadvantaged Women-Owned Small Business (EDWOSB), Service-Disabled Veteran-Owned Small Business (SDVOSB), and Veteran Owned Small Business (VOSB).

Submission Requirements

Interested parties must submit responses electronically to justin.f.figueredo@usace.army.mil and christopher.d.burroughs@usace.army.mil with the subject "Sources Sought – MCR NJ Phase 2 Rehab 2026". Responses are limited to six pages and must include:

  • Firm's name, address, POC, phone, email, CAGE, UEI.
  • Bonding capacity.
  • Business category and size (including small business participation metrics for large businesses).
  • Explanation of capabilities and self-performed work related to the scope.
  • Description of work performed under similar project constraints.
  • Project Examples: 1-3 similar projects (location, stone size/quantity, delivery/placement methods, contract details, customer satisfaction).
  • Joint Venture information (if applicable).
  • Letter from Surety for bonding capability.
  • Firm's interest and likelihood of bidding.
  • Responses to Government's questions (primarily regarding Project Labor Agreements, skilled labor shortages, time-sensitive issues, and market conditions).

Project Constraints & Challenges

The project faces challenges from river/tidal/wave-induced currents, wave breaking risks, high coastal winds, and limited low-tide windows for low-elevation repairs. Construction may pause due to unsafe weather. N Head Rd must be used as the haul road.

People

Points of Contact

Christopher BurroughsPRIMARY
Justin FigueredoSECONDARY

Files

Files

No files attached to this opportunity

Versions

Version 2
Sources Sought
Posted: Mar 2, 2026
View
Version 1Viewing
Sources Sought
Posted: Feb 25, 2026
Mouth of the Columbia River (MCR) North Jetty Rehab Project Phase 2 | GovScope