MT FLAP BLACKF 12(1) FLAP Rehabilitation Two Medicine Road / MT NP GLAC 12(2) FLTP Rehabilitation of Two Medicine Road
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of Transportation, Federal Highway Administration (FHWA), specifically the Western Federal Lands Division, has issued a Presolicitation for the Rehabilitation of Two Medicine Road in East Glacier, MT. This project, identified as MT FLAP BLACKF 12(1) and MT NP GLAC 12(2), is estimated to be between $15,000,000 and $25,000,000 and has a tentative fixed completion date of Fall 2027.
Scope of Work
The work primarily consists of the reconstruction of asphalt pavement roadway, replacement of existing culverts, and mill and overlay of two parking areas, along with other small items of work. The project spans approximately 7.22 miles and is located about 4 miles NW of East Glacier, MT.
Key Requirements / Deliverables
Key aspects of the project include:
- Earthwork: Clearing & Grubbing (21.6 ACRE), Roadway Excavation (11,500 CUYD), Subexcavation (4,500 CUYD), Select Borrow (12,500 CUYD).
- Aggregate & Base Courses: Aggregate Base Grading D (9,500 CUYD leveling, 5,000 CUYD base).
- Asphalt Pavements: Asphalt Concrete Pavement (23,500 TON), Tack Coat (35 TON), Asphalt Pavement Milling (3,500 SQYD).
- Incidental Construction: Various pipe culverts (12-INCH to 120-INCH), end sections, underdrain systems, curb & gutter, sidewalks, and pads.
- Pavement Markings: Extensive markings including solid yellow (69,000 LNFT), solid white (80,000 LNFT), crosswalks/stop lines (300 LNFT), broken yellow (6,800 LNFT), dotted white (1,810 LNFT), "STOP" word message (2 EACH), and accessibility symbols (10 EACH).
- Traffic Control: Temporary traffic control devices including barricades, drums, portable barriers, construction signs, flaggers, and traffic control supervisors.
- Environmental: Streambed Channel Reconstruction (95 LNFT), Wetlands Mitigation (1,100 SQYD).
Contract & Timeline
- Type: Presolicitation
- Product/Service Code: Y1LB (Construction Of Highways, Roads, Streets, Bridges, And Railways)
- Estimated Price Range: $15,000,000 - $25,000,000
- Set-Aside: None specified
- Published Date: March 3, 2026
- Tentative Fixed Completion Date: Fall 2027
Additional Notes
Bidders should refer to the official solicitation once issued for the exact completion date, as per FAR Clause 52.211-10. For inquiries, contact Contracts G. Office at wfl.contracts@dot.gov or 360-619-7520.