Nez Perce-Clearwater NF Salmon River Seed Orchard Well Drilling (2026)
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The USDA Forest Service, specifically the Nez Perce-Clearwater National Forests, is soliciting quotations for Salmon River Seed Orchard Well Drilling in Nezperce, ID. This project aims to provide potable water to the nursery. This is a Total Small Business Set-Aside with quotations due by May 04, 2026, at 12:00 P.M. Mountain Time.
Scope of Work
The primary objective is to drill a well to supply potable water to the Salmon River Seed Orchard nursery. The project includes provisions for potential re-drilling and decommissioning of wells if initial attempts do not meet specified requirements. Work must adhere to provided plans and specifications, including detailed Well Construction Plans (Attachment 3) and Groundwater Well Specifications (Attachment 4). The magnitude of construction is estimated between $100,000 and $250,000. Contractors are highly encouraged to visit the site to familiarize themselves with the layout, though no official site visit will be performed.
Contract Details
- Contract Type: Anticipated Firm Fixed Price.
- Set-Aside: Total Small Business Set-Aside.
- NAICS Code: 237110 Water and Sewer Line and Related Structures Construction, with a small business size standard of $45M.
- Period of Performance: Work shall commence no earlier than October 15, 2026, and conclude no later than October 15, 2027.
- Bonds: A 20% Bid Bond/Offer Guarantee is required for quotes exceeding $150,000. 100% Performance & Payment Bonds are required for contracts over $150,000, due within 10 days of award. For contracts between $35,000 and $150,000, only payment protections (e.g., irrevocable letter of credit) are required.
- Wage Rates: General Decision Number ID20260051 for Heavy Construction in Idaho County, Idaho, applies, detailing prevailing wage rates for various trades.
Submission & Evaluation
- Quotations Due: May 04, 2026, by 12:00 P.M. (Mountain Time).
- Required Documents: Schedule of Items (Attachment 1), Experience Questionnaire (Attachment 6), Bid Guarantee (if applicable), and acknowledgment of any amendments.
- Submission Contact: Daniel Franco at daniel.franco@usda.gov.
- Evaluation Criteria: Quotations will be evaluated based on Experience, Past Performance, and Price.
- Award Basis: Award will be made to the quoter representing the best value to the Government.