NRCS-MA Tyler Dam Rehabilitation Project Floodwater Retarding Dam

SOL #: 12FPC326B0012Combined Synopsis/Solicitation

Overview

Buyer

Agriculture
Farm Production And Conservation Business Center
FPAC BUS CNTR-ACQ DIV
WASHINGTON, DC, 20250, United States

Place of Performance

MA

NAICS

Other Heavy and Civil Engineering Construction (237990)

PSC

Construction Of Restoration Of Real Property (Public Or Private) (Y1QA)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
May 19, 2026
2
Last Updated
May 20, 2026
3
Submission Deadline
Jun 19, 2026, 5:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The USDA Natural Resources Conservation Service (NRCS), through its FPAC Business Center, is soliciting bids for the Tyler Dam Rehabilitation Project Floodwater Retarding Dam in Worchester County, MA. This project aims to rehabilitate the existing dam to comply with current safety and performance standards, specifically addressing inadequate auxiliary spillway capacity. This is a Total Small Business Set-Aside. Bids are due June 19, 2026, at 1:00 PM ET.

Scope of Work

The project involves comprehensive rehabilitation of the Tyler Dam. Key tasks include:

  • Excavating the approach channel upstream of the auxiliary spillway drop structure by 2.5 feet.
  • Installing a geosynthetic clay liner in the auxiliary spillway approach.
  • Raising portions of the dam embankment crest to provide additional freeboard and a uniform crest elevation.
  • Constructing a concrete crest wall where Robin Hill Street intersects the top of the dam.
  • Replacing concrete joint sealant in the auxiliary and principal spillway conduits.
  • Replacing existing chain-link fencing around the auxiliary spillway drop structure.
  • Removing trees within 20 feet of the right upstream embankment groin. Detailed specifications for construction and materials are provided in Attachment 1.

Contract & Timeline

  • Contract Type: Firm Fixed-Price
  • Estimated Value: Between $950,000.00 and $1,100,000.00
  • Period of Performance: Construction completion estimated by November 1, 2026.
  • Set-Aside: 100% Total Small Business Set-Aside
  • Bids Due: June 19, 2026, 1:00 PM ET
  • Questions Due: June 5, 2026, 1:00 PM ET
  • Published Date: May 19, 2026

Site Visit & Requirements

A site visit is scheduled for Wednesday, May 27, 2026, at 10:00 AM ET at the site: 200 Robin Hill Street, Marlborough, MA 01752. Bidders must be registered in SAM.gov. A 20% bid bond is required, and a 100% payment bond (SF-25A, ILC, or Tripartite Escrow) is due within 10 calendar days of award. Wage determinations (MA20260008 and MA20250006) are provided and must be adhered to for labor costs.

Evaluation

Award will be made to the responsible bidder whose bid is conforming and most advantageous to the Government, considering only price. Bids must include all line items; partial bids will be disqualified. Potential unbalanced or unrealistically low prices may lead to rejection.

People

Points of Contact

Mark DomingoPRIMARY

Files

Files

No files attached to this opportunity

Versions

Version 2
Combined Synopsis/Solicitation
Posted: May 20, 2026
View
Version 1Viewing
Combined Synopsis/Solicitation
Posted: May 19, 2026