Oregon/Washington Clamshell Maintenance Dredging 2026
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The U.S. Army Corps of Engineers (USACE), Portland District, has issued a Solicitation for Oregon/Washington Clamshell Maintenance Dredging 2026. This project involves extensive maintenance dredging and material placement across various locations in Oregon and Washington. This is a Total Small Business Set-Aside with an estimated construction magnitude exceeding $10,000,000.00. Proposals are due July 6, 2026, by 02:00 PM local time.
Scope of Work
The project requires clamshell maintenance dredging and material placement at fourteen authorized sites, including four in Oregon (Chetco River, Port Orford, Skipanon River, Oregon Slough) and ten in Washington (Baker Bay, USCG Station Cape Disappointment, Chinook, Skamokawa Creek, Wahkiakum Ferry Channel, Willow Grove Boat Basin, Longview Turning Basin, Old Mouth Cowlitz, Port of Longview, Lower Vancouver Anchorage). Key deliverables include:
- Mobilization and Demobilization
- Dredging approximately 488,100 cubic yards of material
- Placement of dredged materials at designated in-water sites
- Hydrographic and Land Surveys
- Pre/Post Eelgrass Surveys at USCG Station Cape Disappointment
Contract Details
- Contract Type: Firm-Fixed Price (FFP)
- Period of Performance: 10 days for commencement, 284 days for completion after Notice to Proceed (NTP). The overall project period is anticipated from May 1, 2026, to January 31, 2027.
- Estimated Value: Exceeding $10,000,000.00 (cost savings analysis referenced $11.63M).
- Set-Aside: Total Small Business Set-Aside (NAICS Code: 237990, Size Standard: $37,000,000.00).
- Bonds: Performance Bonds and a Bid Guarantee (20% of bid price or $3,000,000.00, whichever is less) are required.
- CMMC: Cybersecurity Maturity Model Certification (CMMC) Level 1 (Self) is required prior to award.
Submission & Evaluation
- Proposal Deadline: July 6, 2026, by 02:00 PM local time.
- Submission Method: Electronic submission via email only.
- Bid Opening: Telephonically scheduled one hour after the bid due date/time.
- Offer Acceptance Period: 120 calendar days.
- Evaluation: Award will be based solely on price and price-related factors.
- Inquiries: All inquiries must be submitted via ProjNet-Bidsm using Inquiry Key: MF3PKZ-A6NP76.
Additional Notes
This requirement is a consolidation of dredging efforts justified for cost-effectiveness, reduced acquisition costs, minimized mobilization/demobilization, and ensuring completion within environmental work windows. Bidders must refer to the detailed plans and specifications, including a relevant Water Quality Monitoring Plan, to ensure compliance with Washington State Water Quality Standards and Section 401 of the Clean Water Act. A pre-solicitation meeting agenda provided insights into project scope, schedule, and key considerations such as third-party surveys, optional CLINs, and accommodating commercial vessel operations.