PIP-II PRECAST CONCRETE SHIELD BLOCKS

SOL #: 379013_MRSolicitation

Overview

Buyer

Energy
Energy, Department Of
FERMILAB - DOE CONTRACTOR
Batavia, IL, 60510, United States

Place of Performance

Batavia, IL

NAICS

Other Concrete Product Manufacturing (327390)

PSC

Clay And Concrete Products Industries Machinery (3630)

Set Aside

No set aside specified

Timeline

1
Posted
Apr 3, 2026
2
Submission Deadline
Apr 30, 2026, 7:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of Energy's Fermilab (Fermi Forward Discovery Group, LLC - FFDG) has issued an unrestricted Solicitation (RFP) for the fabrication and delivery of precast concrete shield blocks for the Proton Improvement Plan II (PIP-II) project. This critical project supports the international Deep Underground Neutrino Experiment. Proposals are due by April 30, 2026, at 2:00 P.M. CST.

Scope of Work

This opportunity requires the manufacture and delivery of 4 PIP-II Absorber Shield Blocks and 58 various PIP-II BTL Shield Blocks. The scope includes furnishing all necessary supervision, labor, materials, tools, transportation, overhead, bonding, safety oversight, and quality control. Manufacturing will occur at the subcontractor's production facility, with delivery to Fermilab in Batavia, IL. Detailed engineering drawings and specifications outline precise requirements for materials (e.g., 5000 psi concrete, Grade 60 rebar, stainless steel embeds), fabrication processes, dimensional tolerances, and quality assurance.

Contract Details

  • Contract Type: Firm-Fixed-Price Subcontract.
  • Set-Aside: Unrestricted.
  • NAICS Code: 327390 (Other Concrete Product Manufacturing Specialty), with a 500-employee small business size standard.
  • Subcontracting Plan: Required for large businesses if the subcontract exceeds $750,000.
  • Delivery: FOB Destination, Fermilab, Batavia, IL.

Submission & Evaluation

  • Proposal Due Date: April 30, 2026, 2:00 P.M. CST.
  • Submission: Proposals must be submitted in two parts: a Technical Proposal and a Business/Cost/Price Proposal, utilizing the provided RFP Document and Pricing Form (Exhibit A).
  • Evaluation Criteria: Award will be based on a "lowest price-technically acceptable" methodology.
  • Technical Factors: Offerors must demonstrate a minimum of five years of experience in precast concrete products, possess PCI certification, and provide evidence of key personnel experience. Additionally, bidders must submit details for three current or past projects of similar size, scope, and complexity completed within the last five years.

Key Dates & Requirements

  • Solicitation Published: April 3, 2026.
  • Questions Due: April 16, 2026, 4:00 P.M. CST.
  • Proposal Validity: Price proposals must be valid for 90 days.
  • Project Milestones (from PO issuance): Submittals (14 calendar days), Delivery Complete (70 calendar days), Project Complete (84 calendar days).
  • Mandatory Certifications: Bidders must complete various certifications, including the Subcontractor Annual Representations & Certifications (SARC) and Proposal Certifications, covering business status, compliance with federal regulations (e.g., Buy American Act, anti-trafficking), and independent price determination.
  • Quality Assurance: A Corporate Quality Assurance Plan is required, or bidders may adopt the provided template.
  • Site Access: All personnel accessing Fermilab facilities must provide Real ID and obtain Fermilab Badging.

Contact Information

For inquiries, contact Michele Reynolds at micheler@fnal.gov or 630-840-2448.

People

Points of Contact

Michele ReynoldsPRIMARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 1Viewing
Solicitation
Posted: Apr 3, 2026
PIP-II PRECAST CONCRETE SHIELD BLOCKS | GovScope