PKA - KC-46 Pallet Shelving - 22 MXS - McConnell AFB
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Air Force has procured KC-46 Pallet Shelving for the 22 MXS at McConnell AFB, Kansas. This acquisition, under a Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside, provides specialized storage for KC-46 463L seat pallets, Air Transportable Galley Lavatories (ATGLs), and ISU 90s.
Scope of Work
The requirement involved the procurement and installation of two distinct shelving units:
- One unit capable of holding 45 passenger seat attached 463L pallets, measuring approximately 157 feet 1 inch long by 7 feet 10 inches wide.
- A second unit designed for 20 ATGLs / ISU 90s, approximately 105 feet long by 7 feet 10 inches wide. Each shelving tier must support approximately 3200 lbs. The contractor was responsible for providing all personnel, materials, equipment, and transportation for installation, including site pre-inspection, debris disposal, and compliance with installation fire and safety regulations. Personnel required background checks and base identification. The contractor was prohibited from using any product or specification requiring Class I Ozone Depleting Substances (ODS).
Contract & Timeline
- Type: Award Notice (for procurement of shelving)
- Set-Aside: Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)
- Award Date: May 27, 2026
- Place of Performance: McConnell AFB, Kansas
- Delivery Timeline: Materials to be delivered no later than 130 calendar days from award.
- Installation Timeline: Installation to be completed no later than 30 calendar days from final material delivery.
- Work Hours: Monday-Friday, 0700-1500, excluding Federal Holidays and Wing down days.
Performance Standards
Shelving units required specific dimensions and built-in dunnage. Equipment was required to function as prescribed by the operating manual.
Additional Notes
The customer (McConnell AFB) was responsible for providing a 15,000 lbs. crane/forklift and a 4,000 lbs. forklift, coordinating site access and escort procedures, and providing space for product/material storage until installation completion. All changes were to be provided in writing by the 22d Contracting Office.