Repair of Fuel System at Bighorn Canyon
SOL #: 140P1426Q0050Combined Synopsis/Solicitation
Overview
Buyer
Interior
National Park Service
IMR NORTHERN ROCKIES(12200)
YELWSTN NL PK, WY, 82190, United States
Place of Performance
Place of performance not available
NAICS
Oil and Gas Pipeline and Related Structures Construction (237120)
PSC
Repair Or Alteration Of Fuel Supply Facilities (Z2NA)
Set Aside
No set aside specified
Original Source
Timeline
1
Posted
Mar 31, 2026
2
Submission Deadline
Apr 14, 2026, 7:00 PM
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The National Park Service (Department of Interior) has issued a Combined Synopsis/Solicitation (RFQ 140P1426Q0050) for the Repair of the Fuel System at Bighorn Canyon National Recreation Area. This 100% Total Small Business Set-Aside opportunity seeks contractors to replace electrical components and exposed fuel lines at the Ok-a-Beh Marina. Quotations are due April 14, 2026, at 13:00 MDT.
Scope of Work
This project involves the replacement of critical electrical monitoring components and above-ground fuel piping for the Ok-a-Beh Marina fuel system. Key tasks include:
- Decommissioning and Removal: Safely remove approximately 75 linear feet of existing flexible fuel piping and electrical components.
- Electrical Installation: Install new Automatic Tank Gauge (ATG), leak detection probe, remote communication unit, and an electrical disconnect sleeve.
- Fuel Piping Installation: Install approximately 130 linear feet of marina-grade, UL-listed fuel piping, including two fuel line disconnects.
- Testing and Commissioning: Conduct comprehensive testing for leak detection, electrical/communication system performance, and fuel flow.
- Site Restoration: Restore disturbed areas and remove all debris. All work must comply with NPS standards, OSHA requirements, and applicable federal, state, and local codes. The place of performance is the Ok-a-Beh Marina, Fort Smith, Montana.
Contract Details
- Contract Type: Firm Fixed Price.
- Set-Aside: 100% Total Small Business.
- NAICS: 237120 (Oil and Gas Pipeline and Related Structures Construction) with a $45M size standard.
- Period of Performance: May 4, 2026, to September 30, 2026.
- Product Service Code: Z2NA (Repair Or Alteration Of Fuel Supply Facilities).
Submission & Evaluation
- Quotations Due: April 14, 2026, at 13:00 MDT.
- Submission Method: Email to Stacy_Vallie@nps.gov.
- Evaluation Factors: Award will be made to the responsible offeror whose proposal is most advantageous to the Government, based on:
- Price.
- Technical Capability: Requires a project narrative (max 2 pages) addressing Quality Control, Safety, Management/Key Personnel, proposed on-site supervisor, staffing, communication, and employee accountability.
- Prior Experience: Requires at least three prior projects of similar size and scope.
- Eligibility: Offerors must be registered in SAM and be a small business at the time of submission, award, and throughout contract performance.
Key Dates & Notes
- Published Date: March 31, 2026.
- Site Visit: A site visit is scheduled for April 8, 2026, at 10:00 a.m. Mountain Time at the Ok-a-Beh Marina.
- Attachments: Include a detailed Scope of Work, a DOL Wage Determination (Service Contract Act), and a template for the Limitations on Subcontracting Report.
People
Points of Contact
Vallie, StacyPRIMARY
Files
Versions
Version 1Viewing
Combined Synopsis/Solicitation