REPLACE CONDUIT AND WIRING FOR STREET LIGHTS, BUILDING 370, DAM NECK ANNEX
SOL #: N4008525R0044Solicitation
Overview
Buyer
Dept Of Defense
Dept Of The Navy
NAVFACSYSCOM MID-ATLANTIC
NORFOLK, VA, 23511-0395, United States
Place of Performance
Virginia Beach, VA
NAICS
Commercial and Institutional Building Construction (236220)
PSC
Repair Or Alteration Of Other Administrative Facilities And Service Buildings (Z2AZ)
Set Aside
8(a) Set-Aside (FAR 19.8) (8A)
Original Source
Timeline
1
Posted
Feb 18, 2026
2
Last Updated
Mar 4, 2026
3
Submission Deadline
Mar 14, 2026, 6:00 PM
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Navy / NAVFACSYSCOM MID-ATLANTIC is soliciting proposals for a task order to replace conduit and wiring for street lights at Building 370, Dam Neck Annex, Virginia Beach, VA. This is an 8(a) Set-Aside opportunity, exclusively for contractors within MACC Group ID: ML-C00075. The project is estimated to be between $250,000 and $500,000. Proposals are due March 4, 2026, at 2:00 PM EDT.
Scope of Work
The contractor will be responsible for restoring power to 16 inoperable street lights. This includes:
- Utilizing directional boring for approximately 2000 linear feet of new conduit and appropriate gauge wiring. Existing conduit paths cannot be reused.
- Demolishing 16 deteriorated light poles and installing new ones. The government will provide the new light poles and fixtures, which must be amber-colored LED, U0 BUG rated, and wildlife compliant (<3000K) per UFC 3-530-01.
- Making all necessary wire connections, re-energizing electrical power, and testing lights for proper operation (e.g., insulation resistance, voltage drop, continuity).
- All work must adhere to manufacturer's specifications, the latest NEC codebook, NFPA-70, UFCs, UFGSs, and OSHA safety standards.
- Field verification of existing conditions and power sources is required, as no as-built drawings are available.
- Demolished materials must be disposed of off-site, coordinating with NAVFAC environmental waste managers.
Contract Details & Timeline
- Contract Type: Task Order under an IDIQ Multiple Award Construction Contract (MACC).
- Set-Aside: 8(a) Set-Aside (FAR 19.8). Restricted to MACC Group ID: ML-C00075.
- Estimated Value: $250,000 - $500,000.
- Period of Performance: 180 calendar days from Task Order Award.
- Liquidated Damages: $297.39 per calendar day of delay.
- Proposal Due Date: March 4, 2026, at 2:00 PM EDT.
- Proposal Validity: 300 calendar days for Government acceptance.
- Place of Performance: Naval Air Station Oceana, Dam Neck Annex, Virginia Beach, VA.
Submission & Evaluation
- Evaluation Criteria: Lowest price to the Government.
- Required Submissions: Proposals must include a cover page, the revised Attachment G Price Schedule Form (REV 2), acknowledged amendments, a copy of Reps & Certs from SAM.gov, a completed Provision 52.204-24 (Attachment I), and a Bid Bond.
- Bid Guarantee: Required, equal to at least 20% of the offer price or $3,000,000, whichever is less.
- Performance and Payment Bonds: Required within 10 calendar days after award.
- Wage Determination: The updated VA20260167 (dated 01/02/2026) specifies prevailing wage rates and fringe benefits for this project, which bidders must incorporate into their cost proposals.
Special Requirements
- Base Access: Contractors must follow specific procedures for personnel and vehicle access to NAS Oceana and Dam Neck Annex, including submitting sponsor verification spreadsheets and SECNAV 5512/1 forms.
- Contact: Abigail Reed, abigail.m.reed13.civ@us.navy.mil, 757-433-1029.
People
Points of Contact
Abigail ReedPRIMARY
Files
Versions
Version 2
Solicitation
Posted: Mar 4, 2026
Version 1Viewing
Solicitation
Posted: Feb 18, 2026