REPLACE ECP CANOPY, BLDG 380, DAM NECK ANNEX
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Navy, NAVFACSYSCOM MID-ATLANTIC, has issued a Solicitation for the design and construction of a new canopy roof system at the Entry Control Point (ECP) of Building 380, Dam Neck Annex, Oceana Naval Air Station, Virginia Beach, Virginia. This project, titled "REPLACE ECP CANOPY, BLDG 380, DAM NECK ANNEX," is a 8(a) Sole Source (FAR 19.8) opportunity, specifically limited to contractors in MACC Group ID: ML-C00075. The new canopy, approximately 5,600 square feet, must utilize existing columns and foundations, providing sun and rain protection while minimizing disruption to gate operations. Proposals are due by March 19, 2026, at 2:00 PM EDT.
Scope of Work
The contractor will be responsible for the design and construction of a new canopy roof system. Key requirements include:
- Utilizing the ten existing columns and foundations.
- Constructing a roof system of approximately 5,600 square feet, maintaining similar extents to the previous structure.
- Providing sun and rain protection for users of the Naval Special Warfare Development Group (NSWDG) Entry Control Point.
- Minimizing disturbance to gate operations during construction.
- Complying with NAS Oceana Installation Appearance Plan (IAP) and specific UFC standards (4-010-01 for Antiterrorism, 4-022-01 for Security Engineering).
- Engaging a Virginia-licensed Professional Engineer as the Designer of Record (DOR).
- Providing a manufacturer no-dollar-limit 20-year watertightness warranty for the total roof system and a minimum two-year contractor warranty for installation workmanship.
- Demolition of existing temporary lighting fixtures, conduit, wire, and associated supports is required.
Contract Details
- Contract Type: Solicitation (Task Order under 8(a) MACC)
- NAICS Code: 236220 - Commercial and Institutional Building Construction
- Estimated Budget: $1,000,000 to $5,000,000
- Completion Period: 487 calendar days from task order award
- Liquidated Damages: $500.25 per calendar day of delay
- Wage Rates: Subject to Department of Labor General Decision Number VA20260167, effective 01/30/2026, for building construction projects in Virginia Beach, VA.
- Set-Aside: 8(a) Sole Source (FAR 19.8) for MACC Group ID: ML-C00075.
Submission & Evaluation
- Proposal Due Date: March 19, 2026, at 2:00 PM EDT.
- Award Basis: Fair opportunity basis to the responsible offeror offering the LOWEST PRICE.
- Required Submissions: Cover page, price proposal form (specifically Attachment G-REV 2), copy of Reps & Certs from SAM, and completed Provision 52.204-24.
- Bid Guarantees: Required (Standard Form 24) in a penal sum equal to at least 20% of the offer price or $3,000,000, whichever is less.
- Performance and Payment Bonds: Required within ten calendar days after award.
- Proposal Acceptance Period: 180 days from receipt of offers.
- Submission Email: Proposals must be submitted to Abigail Reed at abigail.m.reed13.civ@us.navy.mil.
Key Attachments & Notes
- Site Visit: A site visit was held on Thursday, August 28, 2025. Access instructions for NAS Oceana, Dam Neck Annex, and DEVGRU compound are detailed in Attachment H.
- Wage Determination: The latest wage determination is VA20260167.
- Price Schedule: Bidders must use the revised Attachment G-REV 2 Price Schedule Form and acknowledge all amendments on it.
- Personnel Information: Attachment E (USSOCOM Spreadsheet) may be required for proposed personnel details.
- Telecommunications Provision: Offerors must complete Provision 52.204-24 regarding certain telecommunications and video surveillance services/equipment.
- Clarifications: Responses to Pre-Proposal Inquiries (PPIs) clarify details on drawings, construction methods, security systems, CCTV, foundation verification (not required), and temporary lighting removal. Structural drawings are provided in "N40085-09-D-5027-0005-SOF Canopy.pdf".