Roof Repairs Buildings FC571, FC520, FC525, FC573, and FC574

SOL #: N4008526R9018Combined Synopsis/Solicitation

Overview

Buyer

Dept Of Defense
Dept Of The Navy
NAVFACSYSCOM MID-ATLANTIC
NORFOLK, VA, 23511-0395, United States

Place of Performance

Camp Lejeune, NC

NAICS

Roofing Contractors (238160)

PSC

Repair Or Alteration Of Miscellaneous Buildings (Z2JZ)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Feb 23, 2026
2
Submission Deadline
Mar 25, 2026, 7:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of the Navy, NAVFACSYSCOM MID-ATLANTIC, is soliciting proposals for Roof Repairs at Buildings FC571, FC520, FC525, FC573, and FC574 at Marine Corps Base Camp Lejeune, NC. This project, estimated between $5,000,000 and $10,000,000, is a Total Small Business Set-Aside and is open only to pre-qualified Roofing MACC Contractors. Proposals are due March 25, 2026.

Scope of Work

This project involves the comprehensive removal and disposal of existing roof systems (shingles, edge metal, underlayment) down to the deck, followed by the installation of new roofing. Key tasks include:

  • Replacement of up to 5% of damaged roof decking.
  • Installation of new aluminum drip edge (bone white).
  • Application of a new self-adhering ice and water membrane over the entire roof surface.
  • Installation of new aluminum standing seam metal roofs with vented ridge caps (sandstone for FC520, FC525, FC573, FC574; suede for FC571).
  • Installation of new elastomeric expansion joints, pipe boots, and permanent fall protection.
  • Replacement of flashing elements at penetrations (FC571) and reinstallation of lightning protection (FC571).
  • Repair and refinish areas damaged or disturbed by new work. The new roofing systems must be installed to withstand 150 mph winds in accordance with the Uniform Building Code for North Carolina. The facilities must remain watertight throughout construction, and operations should experience minimal disruption.

Contract Details

  • Contract Type: Combined Synopsis/Solicitation (Firm Fixed-Price implied)
  • Estimated Value: $5,000,000 - $10,000,000
  • Set-Aside: Total Small Business Set-Aside (FAR 19.5)
  • Eligibility: Restricted to Roofing MACC Contractors listed on the General Requirements cover page.
  • Contract Completion: 360 days after award.
  • Liquidated Damages: $880 per Calendar Day.
  • Wage Determination: General Decision Number NC20260010 Building.
  • Award Basis: Lowest Price.
  • Bond Requirements: Vary by proposal value: no bonds for <$35K; payment bond only for $35K+; bid, payment, and performance bonds for $150K+.
  • Buy American Requirement: Applies to Construction Materials.

Key Requirements & Special Conditions

  • Hazardous Materials: Fascia contains lead-based paint, and asbestos inspection surveys must be reviewed. Remediation plans for lead-based paint and asbestos are required prior to construction. Disposal of hazardous materials must comply with federal, state, and local regulations, utilizing the Camp Lejeune Landfill by appointment.
  • Site Access & Operations: Contractor must coordinate site access, staging areas, and any disruptions to building functions with the Contracting Officer's Representative (COR) and Facility Manager. Regular working hours are 0730-1600, Monday through Friday. Work outside these hours requires 15 calendar days' written notice and COR approval.
  • Environmental Compliance: Contractors must adhere to the "Contractor Environmental Guide" for MCB Camp Lejeune, covering EMS, hazardous materials/waste, stormwater, and emergency response. UXO awareness training is required for ground-disturbing activities.
  • Technical Specifications: Detailed specifications for Aluminum Standing Seam Roofing (07 61 15.00 20) outline material, system description, performance (e.g., wind/water resistance), submittals, installation, and warranty requirements (30-year material, 2-year installation, 130-150 mph wind).
  • Utilities: Contractor is responsible for obtaining professional utility locator services, verifying elevations, and notifying COR 48 hours prior to excavation. Damage to existing utilities is the contractor's responsibility.

Submission & Evaluation

  • Proposal Due Date: March 25, 2026, by 3:00 PM EST.
  • Requests for Information (RFIs) Cut-off: March 10, 2026, by 4:00 PM EST.
  • Submission Email: emily.a.walton6.civ@us.navy.mil AND lauren.f.loconto.civ@us.navy.mil.
  • Site Visit: A site visit is scheduled for Thursday, February 26, at 9:00 AM, meeting at Building FC525.
  • Evaluation: Offers will be evaluated by adding prices for all Exhibit Line Item Numbers (ELINs 0001-0005). Bidders must submit offers on all line items; failure to do so may result in rejection.
  • Proposal Acceptance Period: 60 days from receipt of offers.

Points of Contact

People

Points of Contact

Files

Files

Download
Download
Download
Download
Download
Download
Download

Versions

Version 1Viewing
Combined Synopsis/Solicitation
Posted: Feb 23, 2026
Roof Repairs Buildings FC571, FC520, FC525, FC573, and FC574 | GovScope