Tionesta Dam Control Tower Concrete Repair

SOL #: W911WN26QA043Pre-Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W072 ENDIST PITTSBURGH
PITTSBURGH, PA, 15222-4198, United States

Place of Performance

Tionesta, PA

NAICS

Other Heavy and Civil Engineering Construction (23799)

PSC

Construction Of Restoration Of Real Property (Public Or Private) (Y1QA)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Jun 8, 2026
2
Response Deadline
Jun 23, 2026, 9:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The U.S. Army Corps of Engineers, Pittsburgh District, has issued a Pre-Solicitation Notice for the Tionesta Dam Control Tower Concrete Repair project in Tionesta, PA. This opportunity is a 100% Small Business Set-Aside for a Firm-Fixed Price (FFP) contract. The Request for Quote (RFQ) is anticipated to be issued on or about June 24, 2026, via PIEE and SAM.gov.

Scope of Work

The project involves critical repairs to a deteriorated concrete section within the stairwell of the Intake Tower at Tionesta Creek Lake. The primary goal is to restore watertightness, prevent interior inundation during high-water events, and ensure safe access for personnel. Specific tasks include:

  • Concrete Sounding and Demolition: Identifying and removing unsound concrete material (approximately 8 ft high, 7 ft wide, and at least 8 inches deep).
  • Grout Installation: Applying non-shrink, low-pressure injection grout around the perimeter to reduce seepage.
  • Reinforcement: Installing horizontal, vertical, and bent-hook bars, doweled and epoxied into the existing structure, maintaining a minimum three-inch clear cover.
  • Surface Preparation: Applying a concrete bonding agent to existing surfaces.
  • Waterstop Installation: Placing a hydrophilic waterstop along all vertical and horizontal joints to minimize future leakage.
  • Concrete Placement: Setting formwork flush with the existing wall face and placing/vibrating new concrete for full consolidation and a uniform finish.

Contract & Timeline

  • Contract Type: Firm-Fixed Price (FFP)
  • Set-Aside: 100% Small Business Set-Aside
  • NAICS: 237990 – Other Heavy and Civil Engineering Construction (Size Standard: $45,000,000)
  • Period of Performance (POP): 365 Calendar Days after Notice to Proceed (NTP)
  • RFQ Release: On or about June 24, 2026
  • Published Date: June 8, 2026

Key Requirements & Registration

To be considered for award, contractors must:

  • Have an active registration in the System for Award Management (SAM.gov). Registration can take at least 10 business days and must be renewed annually.
  • Be registered in the Procurement Integrated Enterprise Environment (PIEE) Solicitation Module with the PROPOSAL MANAGER Role.
  • Possess a current (not more than three years old) NIST SP 800-171 DoD Assessment on record in the Supplier Performance Risk System (SPRS). Companies are encouraged to complete this assessment via SPRS prior to the RFQ due date.

Small businesses are encouraged to utilize APEX Accelerators for free assistance with government contracting. For SAM.gov assistance, contact the Federal Service Desk (866-606-8220). For PIEE assistance, contact the PIEE help desk (866-618-5988).

Contact Information

People

Points of Contact

Files

Files

No files attached to this opportunity

Versions

Version 1Viewing
Pre-Solicitation
Posted: Jun 8, 2026
Tionesta Dam Control Tower Concrete Repair | GovScope