Urgent Beach Nourishment Cape May Inlet to Lower Township Cape May, Cape May County, NJ

SOL #: W912BU26BA019Pre-Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W2SD ENDIST PHILADELPHIA
PHILADELPHIA, PA, 19103-0000, United States

Place of Performance

NJ

NAICS

Other Heavy and Civil Engineering Construction (237990)

PSC

Construction Of Other Conservation And Development Facilities (Y1KZ)

Set Aside

No set aside specified

Timeline

1
Posted
Mar 18, 2026
2
Response Deadline
Apr 6, 2026, 5:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The U.S. Army Corps of Engineers (USACE), Philadelphia District, anticipates a requirement for urgent beach nourishment at Cape May Inlet to Lower Township Cape May, Cape May County, NJ. This is a Pre-solicitation Notice for planning and information purposes only; a formal solicitation (W912BU26BA019) is expected around April 7, 2026. The project is estimated to be between $10M and $20M.

Scope of Work

The project involves beach nourishment along the Atlantic coast of New Jersey, specifically from the Cape May Inlet southwest jetty to the 3rd Ave terminal groin in Cape May City. This includes the communities of Cape May City, Lower Township, and the US Coast Guard Training Center.

The base bid will include:

  • Pre-placement condition surveys.
  • Pumping and placing approximately 364,000 cubic yards of sand from an offshore borrow area (2.6 miles south of Cape May Inlet jetties) onto two beach locations:
    • Area 1: US Coast Guard Training Center (approx. 330,000 CY).
    • Area 2: Wilmington Ave (approx. 34,000 CY). Options for additional sand placement from the same borrow area to achieve the full project design template are also included, totaling several hundred thousand additional cubic yards for Area 1 and Area 2. Sand must originate from the offshore borrow area; trucking is not permitted.

Contract & Timeline

  • Opportunity Type: Pre-solicitation Notice
  • Solicitation Release: Anticipated on or around April 7, 2026 (Solicitation W912BU26BA019).
  • Magnitude: Between $10,000,000 and $20,000,000.
  • NAICS: 237990, Dredging and Surface Cleanup Activities (Size Standard: $37.0M).
  • Set-Aside: Full and Open (Unrestricted), with a HUBZone 10% price evaluation preference (FAR 19.1307).
  • Period of Performance: 110 calendar days from Notice to Proceed (NTP).
  • Environmental Restrictions: No work permitted between March 1st and August 31st.
  • Published: March 18, 2026.

Additional Information

This notice is for planning and information only and is not a commitment by the Government. The Government will not pay for responses to this notice. Potential bidders are responsible for monitoring SAM.gov for the official solicitation, amendments, and updates.

Point of Contact

For written communication regarding this notice, contact Molly Gallagher at molly.gallagher@usace.army.mil. Include the solicitation number, company name, address, phone number, and point of contact.

People

Points of Contact

Molly GallagherPRIMARY
Brandon MormelloSECONDARY

Files

Files

No files attached to this opportunity

Versions

Version 1Viewing
Pre-Solicitation
Posted: Mar 18, 2026
Urgent Beach Nourishment Cape May Inlet to Lower Township Cape May, Cape May County, NJ | GovScope