Timeline
1
Posted
Jul 25, 2019
2
Last Updated
Aug 26, 2019
3
Response Deadline
Aug 26, 2019, 8:00 PM
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Hopper dredging of Brazos Island Entrance and Jetty Channels. Estimated quantity of maintenance material is 510,000 CY. Dredged material to be placed on South Padre Island beneficial use beach placement areas #1 and #5. Material to be split 25/75 between BUPA #1 and BUPA #5. BUPA #1 is located just North of the North BIH Jetty and BUPA #5 is located approximately 5 miles North of the North Jetty.; Option 1: Placement at BIH upland confined PA 2 in lieu of PA 1A/1B.
The solicitation is being issued, and the response date is 26 August 2019 @ 2:00 PM (CST) (All bids must be submitted electonically via www.FBO.gov). The estimated award date of this project is 9 September 2019.
The solicitation is being issued, and the response date is 26 August 2019 @ 2:00 PM (CST) (All bids must be submitted electonically via www.FBO.gov). The estimated award date of this project is 9 September 2019.