Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The USDA Forest Service is soliciting bids for the replacement of Bridge 521-2.9 over Bear Creek in the Kisatchie National Forest, Grant County, Louisiana. This is an Invitation for Bid (IFB) for a firm-fixed price contract under a Total Small Business Set-Aside. The project involves constructing a permanent 2-span bridge. Bids are due May 22, 2026, at 0900 CT.
Scope of Work
The contractor will provide all materials, labor, equipment, and supervision to replace the existing bridge on National Forest Road (NFSR) 521-2.9. The work must adhere to FP-24 Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects and Forest Service Supplemental Specifications. Key tasks include:
- Mobilization of personnel, material, and equipment.
- Removal of the existing bridge (piles below grade).
- Structural backfill and excavation.
- Placement of Class 2 Riprap (La DOTD Class 130).
- Crushed aggregate surfacing course.
- Installation of 14" x 14" prestressed concrete piles.
- Structural concrete (Class A) and various precast concrete members (abutment, pier, wingwall, backing plank).
- Prestressed structural concrete members and Grade 60 reinforcing steel.
- Construction of a bridge traffic barrier curb, seeding, wood posts, and object markers.
Contract Details
- Contract Type: Firm-Fixed Price
- Award Basis: Lowest Price Responsive/Responsible
- Number of Awards: One (1)
- Set-Aside: Total Small Business Set-Aside (FAR 19.5)
- NAICS: 237310 Highway, Street, and Bridge Construction
- Magnitude: Between $500,000 and $1,000,000
- Period of Performance: Approximately 180 days after award, through December 31, 2026.
Submission & Evaluation
- Questions Deadline: April 30, 2026. Submit to Richard.huffman@usda.gov and cc: Charles.cotton@usda.gov with subject '12445126B0016 QUESTION'.
- Bids Deadline: May 22, 2026, 0900 CT. Email bids to Richard.huffman@usda.gov and cc: Charles.cotton@usda.gov. Subject line: '12445126B0016 BID_Co. Name'.
- Confirmation: Contractors must call the Contracting Officer/Contract Specialist to confirm receipt of their bid.
- Evaluation: Award will be made to the lowest price that is responsive and responsible, in accordance with FAR 14.306.
- Offer Acceptance Period: 90 calendar days from the bid due date.
Additional Notes
- Site Visit: No organized site visit. Contractors are required to self-tour the bridge, which is currently closed to all traffic, and certify inspection on Schedule B. Failure to inspect will not constitute grounds for a claim.
- Bid Guarantee: Required (FAR 52.228-1).
- Performance & Payment Bonds: Required (SF-25A and SF-25), 100% of award price, due 10 days after award.