Warm Waste Pond

SOL #: INL-26-020Sources Sought

Overview

Buyer

Energy
Energy, Department Of
BATTELLE ENERGY ALLIANCE–DOE CNTR
Idaho Falls, ID, 83415, United States

Place of Performance

Idaho Falls, ID

NAICS

No NAICS code specified

PSC

No PSC code specified

Set Aside

No set aside specified

Timeline

1
Posted
Feb 17, 2026
2
Response Deadline
Mar 18, 2026, 5:59 AM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Battelle Energy Alliance, LLC (BEA), the Management & Operating Contractor for the U.S. Department of Energy's (DOE) Idaho National Laboratory (INL), is seeking Expressions of Interest (EOI) from qualified vendors for the construction of a new lined warm waste pond at the Advanced Test Reactor (ATR) Complex in Idaho Falls, ID. This EOI serves as the initial step to identify potential bidders for a future formal Request for Proposal (RFP). Responses are due by March 17, 2026.

Scope of Work

The project involves constructing a new lined warm waste pond, approximately 25% larger than existing individual ponds, to expand capacity and enhance resiliency for ongoing ATR operations. The anticipated scope of work includes:

  • Subgrade preparation and installation of CSPE-R primary geomembrane liner, including anchor trenches and seam QA/QC.
  • Installation of an HDPE secondary liner (double-lined system) with leak-detection layers and monitoring infrastructure.
  • Extension of existing gravel roads for construction access and long-term operations.
  • Extension of existing chain-link fences and security features around the new pond.
  • Installation of power service for monitoring, pumping, and controls.
  • Extension of the existing discharge line with required tie-ins and isolation.
  • Implementation and testing of a leak detection system and redundant pumping system, including controls integration. Vendors must comply with applicable federal, state, and local requirements, as well as INL site procedures and quality programs.

Opportunity & Timeline

  • Type: Expression of Interest (EOI) / Sources Sought
  • Set-Aside: None specified
  • Response Due: March 17, 2026
  • Published: February 17, 2026
  • Place of Performance: Idaho Falls, ID

Submission Requirements

Interested vendors should submit an EOI that includes:

  • Company name and point of contact.
  • Description of relevant capabilities and experience in earthwork and pond construction; CSPE-R and HDPE geomembrane installation; double-liner leak-detection systems; industrial pumping and controls; civil/site work (roads, fencing); and pipeline extensions in industrial settings.
  • NAICS codes and business size classification.
  • Any existing DOE or federal contracting experience (if applicable). Submissions should be sent to Chase.Egbert@inl.gov.

Evaluation & Next Steps

This EOI is for market research purposes to identify interested and qualified vendors. Responses will be used to inform the development of a formal solicitation list. Only selected respondents, as determined by BEA, will receive an invitation to participate in the anticipated RFP process for award consideration.

Additional Notes

Information submitted in response to this EOI may be business sensitive or proprietary and should be marked accordingly.