WWYK150185 - REPAIR ROADWAYS, PARKING AT MUNITIONS AREA & WWYK190230 - REPAIR ARNOLD AVE BETWEEN H AVE AND M AVE

SOL #: FA813726R0027Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Air Force
FA8137 AFSC PZIOC
TINKER AFB, OK, 73145-9125, United States

Place of Performance

Oklahoma City, OK

NAICS

Highway (237310)

PSC

Repair Or Alteration Of Highways/Roads/Streets/Bridges/Railways (Z2LB)

Set Aside

Women-Owned Small Business (WOSB) Program Set-Aside (FAR 19.15) (WOSB)

Timeline

1
Posted
Apr 30, 2026
2
Last Updated
Jun 12, 2026
3
Submission Deadline
Jul 24, 2026, 7:00 AM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of the Air Force is soliciting proposals for two construction projects at Tinker Air Force Base, Oklahoma: FA813726R0027. This 100% Women-Owned Small Business (WOSB) Set-Aside opportunity involves the repair of roadways and parking at the Munitions Area (WWYK150185) and the repair of Arnold Avenue (WWYK190230). The projects will be awarded as a single Firm Fixed-Price contract. Proposals are due July 24, 2026, at 2:00 PM CST.

Scope of Work

This solicitation covers two distinct but related construction efforts:

  • WWYK150185 - Repair Roadways, Parking at Munitions Area: This project entails furnishing all materials, labor, and equipment to repair roadways and parking lots near buildings B3812 and B3804, including the expansion and repair of the B3812 entrance. Work involves demolition, excavation, and construction of new pavement profiles with subgrade modification, aggregate base, separation fabric, and asphalt layers.
  • WWYK190230 - Repair Arnold Ave between H Ave and M Ave: This project requires full depth pavement replacement and mill & overlay of Arnold Avenue. The work is phased, covering eastbound and westbound lanes, curb and gutter replacement, new drainage structures, sidewalk replacement, pavement markings, and electrical work including new LED streetlights.

Both projects require adherence to specific performance standards, quality control measures (per spec 01 45 00.00 10), and health and safety protocols (EM 385-1-1).

Contract Details

  • Contract Type: Firm Fixed-Price.
  • Estimated Magnitude:
    • WWYK150185: $500,000 - $1,000,000
    • WWYK190230: $1,000,000 - $5,000,000
  • NAICS Code: 237310 (Road, Highway, and Street Construction) with a $45 million size standard.
  • Performance Period: 250 calendar days after receipt of Notice to Proceed for each project.
  • Funding: Award is contingent upon the availability of appropriated funds.
  • Wage Determination: Prevailing Davis Bacon Wage Determination (OK20260049) will be incorporated.

Submission & Evaluation

  • Proposal Submission: Offers must be submitted electronically in an unlocked Microsoft Excel spreadsheet format for pricing, broken out by CSI division or salient features. Technical proposals must be specific, complete, and address capability, management, schedule, and planning. Independent offers are required for each project, though they will be combined into a single contract.
  • Evaluation Criteria: This is a Lowest Price Technically Acceptable (LPTA) acquisition. Proposals will be evaluated for technical acceptability (work plan, technical risk, capability, management, schedule, planning) and contractor responsibility in SAM. Award will be made to the lowest priced, technically acceptable offer from at least two proposals.
  • Bonds: Performance and Payment Bonds are required within 10 calendar days after award.
  • Validity: Proposals must be valid for 120 calendar days.

Key Dates & Site Visit

  • Mandatory Initial Site Visit RSVP: Email to contracting points of contact by June 10, 2026, at 2:00 PM CT. Attendees must have base access or submit an Entry Access List (EAL) with the RSVP. Attendance at the site visit is mandatory for proposal eligibility.
  • Proposal Due Date: July 24, 2026, at 2:00 PM CST.
  • Questions: Submit written questions to darian.permetter@us.af.mil.

Special Requirements & Attachments

Contractors must adhere to Tinker AFB's specific standards for electrical, mechanical, fire protection, and general facility construction. Key personnel (Project Manager, Quality Control Manager, Site Safety and Health Officer, Project Superintendent) with specific experience are required. All personnel require AFMC Form 387 identification cards and FOD awareness training. Work in airfield operations areas requires pre-coordination and an 'Airfield Construction Waiver'. Submittal registers for both projects detail extensive documentation requirements.

People

Points of Contact

Darian PermetterPRIMARY
Tamra TorresSECONDARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 6
Solicitation
Posted: Jun 12, 2026
View
Version 5Viewing
Solicitation
Posted: Jun 3, 2026
Version 4
Solicitation
Posted: Jun 2, 2026
View
Version 3
Pre-Solicitation
Posted: Jun 2, 2026
View
Version 2
Pre-Solicitation
Posted: May 4, 2026
View
Version 1
Pre-Solicitation
Posted: Apr 30, 2026
View