Y--Weld Substation Stage 05

SOL #: 89503226BWA000074Pre-Solicitation

Overview

Buyer

Energy
Energy, Department Of
WESTERN-ROCKY MOUNTAIN REGION
LOVELAND, CO, 80538, United States

Place of Performance

Place of performance not available

NAICS

Power and Communication Line and Related Structures Construction (237130)

PSC

Construction Of Other Non Building Facilities (Y1PZ)

Set Aside

No set aside specified

Timeline

1
Posted
May 20, 2026
2
Response Deadline
Jul 15, 2026, 8:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), under the Department of Energy, is issuing a Presolicitation for the Weld Substation Stage 05 Construction Project. This project aims to enhance WAPA's electrical power reliability by replacing the end-of-life KV1A transformer and station service. This will be a Sealed Bidding Solicitation (FAR Part 14), with responses accepted only via FedConnect. The estimated magnitude of construction is Between $1M and $5M. The solicitation is anticipated to be issued on or about June 9, 2026, with responses due by July 15, 2026.

Scope of Work

The project involves comprehensive construction services at the Weld Substation in Greeley, CO. Key components include:

  • Removal and installation of a 230/115-13.8-KV, 150MVA, transformer KV1A.
  • Removal and installation of associated 230/115KV take-off structure and KV1A tertiary station service feed.
  • Installation of a new station service and removal of the existing one.
  • Installation of new KV2A tertiary station service feed.
  • Associated foundations, structures, and electrical equipment.
  • Removal of control building single-phase AC panels and installation of 3-phase AC panels.
  • Site development for Weld Substation, Stage 05.

Contract & Timeline

  • Type: Sealed Bidding Solicitation (FAR Part 14)
  • Set-Aside: 100% Small Business Set-Aside
  • NAICS: 237130 (Electrical Power Generation, Transmission and Distribution Construction)
  • Size Standard: $45.0 Million
  • Estimated Value: Between $1M and $5M
  • Period of Performance: 700 calendar days after Notice to Proceed
  • Anticipated Solicitation Release: On or about June 9, 2026
  • Response Due: July 15, 2026 (20:00:00Z)
  • Published Date: May 20, 2026

Important Notes

  • All responses must be submitted via FedConnect ONLY; email proposals will not be accepted.
  • The Buy American Act applies. Bidders must refer to FAR Clause 52.225-9 (Section I) and FAR Provision 52.225-10 (Section L) and identify any non-domestic materials in their bid.
  • The new KV1A transformer was ordered in 2023 and is expected for delivery in 2027.

Contact Information

  • Primary Contact: John W. Pratt
  • Email: jpratt@wapa.gov
  • Phone: 720-962-7166

People

Points of Contact

Pratt, John W.PRIMARY

Files

Files

View

Versions

Version 1Viewing
Pre-Solicitation
Posted: May 20, 2026