Y1DA--528A6-26-611 Abate Asbestos Pipe Insulation - B76
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Abate Asbestos Pipe Insulation – B76
528A6-26-611
GENERAL PROJECT WORK SCOPE DESCRIPTION
Existing Conditions:
The Bath VAMC is located at 76 Veterans Avenue, Bath, NY 14810. The layout is a campus
with more than 30 buildings located on over 200 acres. Normal working hours are Monday – Friday
8:00am – 4:30pm. The Scope of this project includes but is not limited to the abatement of ACM
pipe insulation found within Building 76. Contactor shall follow all requirements and procedures set
by the local, state, and federal rule, regulation, and guidelines for the proper removal and disposal of
ACM. Building 76 being a fully operational Medical Center may restrict the hours of work and may
require off-tour work to ensure continuous operations of the facility as directed by the COR.
Contractor shall have 30 days from the “Notice to Proceed” to complete all work.
Scope of Work:
1. Demolition:
a. Contractor is to provide all labor, material, equipment, supervision, to complete the
removal of approximately 200 LF of ACM insulation found on existing plumbing
from the crawl space and runs vertically through to the 2nd floor. Contractor is
required to dispose of all ACM at an approved location offsite. Clear exposure/wall
removal is to be completed by Medical Center maintenance shops prior to the start of
the abatement.
b. Part of scheduled abatement work is within basement/crawl space which is
considered a confined space.
2. Safety Measures:
a. Review and incorporate risk assessment and interim life safety plans and measures
into safety and construction planning.
i. Pre Construction Risk Analysis (PCRA) by VA
ii. Interim Life Safety Measures (ILSM) by VA
b. Generate and follow a safety plan and incorporate risk and life safety assessments.
3. Communication and Standards
a. All contract direction, changes, financials, and contract performance are the
responsibility of the VAMC Contracting Officer (CO).
b. Contracting Officers Technical Representative (COR) is responsible for the day-today
operations in project and the primary point of contact (POC) for the project.
i. Communications to/from VAMC
ii. Technical communications, submittals, RFI’s, change orders
iii. On site visits for construction and sub-contractors
iv. Construction coordination
c. Project is required to use Autodesk Construction Cloud Build Platform (ACC)
i. Bath VAMC will provide licensing, permissions, and online training for this
cloud-based tool at no cost to the contractors.
ii. Contractors are required to actively use Build on ACC for project
documentation and coordination.
iii. ACC is used for submittals, RFI’s, project communications and
documentation.
1. No contract financial information on ACC.
2. No personal identification information on ACC.
Code requirements:
The installed product must, at a minimum, be in accordance with all applicable codes
including Veterans Affairs standards which can be found at https://www.cfm.va.gov/til/. This will
include, but not be limited to: Department of Veterans Affairs Design Manuals, VA Publications,
and Construction Standards, National Fire Protection Code (NFPA), Life Safety Code, Underwriters
Laboratory (UL), International Building Code IBC, National Electric Code (NEC), the VA
Information Security Handbook 6500.6, Occupational Health and Safety (OSHA), and
Environmental Protection Agency (EPA) requirements (to include Mold Remediation in Schools and
Commercial Buildings). All work will be completed by certified individuals.
Contract Drawings: Please see attached.
Specifications: Please see attached.
General Requirements:
A. The contractor shall review the contract documents for conflicts. Where conflicts exist work
shall not proceed until the COR has been notified and has given direction.
B. Where incidental work is required to accomplish work shown on the drawings, this work is
implied and shall be included as part of the base bid.
C. Prior to any work commencing in an area, the contractor shall notify the COR of his intention to
work in the area and shall schedule a walkthrough with the COR to determine existing
conditions.
D. After the work, the existing work areas shall be returned to their original state before final
approval shall be given. After the completion of construction, the contractor shall completely
clean all surfaces of construction debris.
E. The contractor shall receive all deliveries of materials, equipment, tools, or other goods off
station, and bring them to the job site. The Bath VA shall not accept deliveries for project
purposes.
F. The contractor shall prepare and submit an excel spreadsheet submittal log listing all submittals
required. The worksheet shall be submitted by the contractor and reviewed and re-submitted as
necessary.
G. The contractor shall not proceed with any on-site work until the completion of the submittal
process or approval to proceed from the CO and COR without completion of the submittal
process. Not less than 14 calendar days shall be planned for COR review of each submittal. Resubmittals
shall be provided as required by the COR, and shall be treated as a new, separate
submittal.
H. Any non-lead time materials will only be paid for when installed.
I. Any items identified as punch list items will be fixed prior to project closeout.
J. Special care will be taken to secure tools and construction equipment during construction as this
facility has patients in it.
K. Work cleanliness must be adhered to throughout the project.
L. Sounds and vibrations must be kept to a minimum to avoid patient disruption. The COR
reserves the right to stop work if sound and vibrations are impacting patient living or employees.
M. Contractor staging area is east of railroad tracks, coordinate with COR.
N. Off tour work may be required to minimize the impact on Veterans and employees.
O. The contractor shall warranty all work including for 1 year from the date of acceptance.
Warranty shall include any labor or parts necessary to ensure complete functionality of the new
area.
P. The contractor shall plan accordingly to stage and store materials in the contractor’s designated
area shown.
Q. The contractor shall be responsible for coordinating any traffic interruption with the COR. The
contractor is responsible for providing interior pedestrian traffic control as well as any exterior
traffic control personnel as needed during the period of the performance.
Submittals:
Submittals are required for all items outlined in the specification and include but are not
limited to the submittals as shown in the submittal log.
Project Duration:
The total project duration for this project is not to exceed 30 days from the date of the NTP
issuance. This includes all processes starting with submission and approval of all submittals and
ending with final punch list c