Solicitation - Y1EZ--Construct Chiller Plant | Design Build Milwaukee, WI VAMC | 695-24-101

SOL #: 36C77626R0024Solicitation

Overview

Buyer

Veterans Affairs
Veterans Affairs, Department Of
PCAC (36C776)
INDEPENDENCE, OH, 44131, United States

Place of Performance

Milwaukee, WI

NAICS

Commercial and Institutional Building Construction (236220)

PSC

Construction Of Other Industrial Buildings (Y1EZ)

Set Aside

No set aside specified

Timeline

1
Posted
Jan 27, 2026
2
Last Updated
Apr 22, 2026
3
Submission Deadline
May 22, 2026, 4:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of Veterans Affairs (VA), specifically the PCAC office, is soliciting proposals for a Design-Build (DB) project to construct a new Chiller Plant at the Clement J. Zablocki VA Medical Center in Milwaukee, WI. This Unrestricted procurement aims to replace the existing undersized chiller plant and upgrade cooling capabilities for the Main Hospital (Building 111). The project magnitude is estimated between $50,000,000 and $100,000,000. The acquisition will follow a two-phase design-build selection process. Phase I technical questions are due by May 5, 2026, 12:00 PM Eastern Time. The overall response date is May 22, 2026.

Purpose & Scope

The primary objective is to furnish all labor, materials, equipment, supervision, and professional architectural, engineering, and construction services for the design and construction of a new approximately 11,500 SF Chiller Plant (Building 153). The scope includes the demolition of Building 109, site preparation, relocation or protection of impacted utilities, installation of upgraded chilled-water capacity, construction of a second-floor walkway connecting to the existing Chiller Plant (Building 113), and provision of full generator backup. The design must integrate all utility connections into existing VAMC systems and meet physical security requirements.

Contract Details

  • Contract Type: Firm-Fixed-Price.
  • Period of Performance: Approximately 730 calendar days from the Notice to Proceed.
  • Magnitude: Estimated between $50,000,000.00 and $100,000,000.00.
  • Set-Aside: Unrestricted.
  • NAICS Code: 236220 (Construction Of Other Industrial Buildings), Size Standard: $45 million.
  • Place of Performance: Clement J Zablocki VA Campus, Milwaukee, WI.

Key Requirements & Deliverables

  • Comprehensive architectural and engineering design services, including 35%, 65%, 95%, and 100% design packages.
  • Compliance with VA Design Guides, Design Criteria, VA Master Specifications, and all applicable codes (IBC, NFPA, OSHA).
  • Specific brand-name items are required for the Building Automation System (Johnson Controls Inc MetaSys), Physical Security Access & Control System (JCI C Cure 9000), Fire Alarm System (Siemens Pytronics), and Door Hardware (Sargent Lockset) due to standardization and compatibility.
  • Adherence to Davis-Bacon Act prevailing wage rates for construction trades.
  • Compliance with VAAR Attachment 12 regarding limitations on subcontracting (e.g., not paying more than 85% of government payment to non-SDVOSB/VOSB firms for general construction, excluding materials).
  • A Project Labor Agreement (PLA) is required after contract award.

Submission & Evaluation

  • This is a two-phase design-build selection process.
  • Phase I proposals will be evaluated on Technical Approach, Technical Qualifications, and Past Performance. A maximum of five Offerors will be selected for Phase II.
  • Phase II proposals will be evaluated on Technical Solution, Draft Project Schedule, Small Business Participation, and Price.
  • Award will be made to the responsible Offeror whose proposal represents the best value to the Government, using a Trade-Offs method.
  • Offerors must submit a completed Past Performance Questionnaire (PPQ) and Project Information Sheet for past projects.
  • A bid bond is required for Phase II proposals.
  • Phase I Technical Questions Due: May 5, 2026, 12:00 PM Eastern Time.
  • Overall Response Date: May 22, 2026, 16:00:00Z.

Contact Information

  • Primary Contact: Shardae Webb, Contract Specialist, Shardae.Webb@va.gov, 216-791-3800 ext 49668.

People

Points of Contact

Shardae WebbContract SpecialistPRIMARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
View
Download

Versions

Version 2Viewing
Solicitation
Posted: Apr 22, 2026
Version 1
Pre-Solicitation
Posted: Jan 27, 2026
View
Solicitation - Y1EZ--Construct Chiller Plant | Design Build Milwaukee, WI VAMC | 695-24-101 | GovScope