Yazoo Backwater Pumping Plant - Industry Day No. 1

SOL #: W912EE26S0004Special Notice

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W07V ENDIST VICKSBURG
VICKSBURG, MS, 39183-3435, United States

Place of Performance

Vicksburg, MS

NAICS

Other Heavy and Civil Engineering Construction (237990)

PSC

Construction Of Other Non Building Facilities (Y1PZ)

Set Aside

No set aside specified

Timeline

1
Posted
Mar 30, 2026
2
Last Updated
May 5, 2026
3
Action Date
Apr 21, 2026, 7:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The US Army Corps of Engineers (USACE) Vicksburg District is hosting an Industry Day on April 23, 2026, for the Yazoo Backwater Pumping Plant project in Vicksburg, MS. This event seeks industry input to inform the design and acquisition planning for three potential construction contracts, including a $1B+ Pumping Plant Construction effort. Responses to the Request for Information (RFI) and Industry Day pre-registration are due by April 21, 2026.

Purpose of Industry Day

This Industry Day is a market research event to gather input from qualified and capable contractors for the Yazoo Backwater Pumping Plant project. The project is in its early design stages, and industry feedback will inform final designs and acquisition planning.

Project Scope & Potential Contracts

The project involves the construction of a 25,000 CFS pumping plant adjacent to the Steele Bayou Drainage Structure to manage water levels in the Yazoo Backwater Area. The current design is 10% conceptual. The USACE anticipates three major construction contract opportunities:

  • Inlet and Outlet Channel Excavation: Up to $50M.
  • Foundation & Site Development: Up to $100M.
  • Pumping Plant Construction: Over $1B, including supply, installation, and start-up of 14 axial-flow pumps.

Acquisition Strategy Insights

The USACE is considering specific acquisition approaches:

  • Site Preparation/Foundation and Channel Excavation (Contracts #1 & #2): May be awarded via Competitive Best Value Trade Off (BVTO) Single Award Task Order Contracts (SATOCs), potentially combined.
  • Pumping Plant Construction (Contract #3): A two-phase strategy is proposed, involving Pre-Qualification of Sources followed by a competitive solicitation for pre-qualified firms, with Early Contractor Involvement (ECI).

Industry Day & One-on-One Details

The Industry Day will be held on April 23, 2026, at 9:00 AM CST at the USACE Vicksburg District Headquarters (4155 Clay Street, Vicksburg MS 39180), with both in-person and virtual attendance options. One-on-one sessions for prime contractors only will be held from April 27 to May 1, 2026, to receive individual input on project designs and procurement planning. These are not for general capability briefings.

Submission Requirements & Deadlines

  • Pre-registration for Industry Day: Complete and return the attached form by April 21, 2026.
  • Requests for One-on-One Sessions: Email Kasey Davis by April 23, 2026. Availability is first-come, first-served.
  • Written Responses to RFI Questions: Submit a capabilities package (corporate, past performance, technical, acquisition questions) via email to Kasey Davis (Kasey.T.Davis@usace.army.mil) and R. Ellis Screws (Ellis.Screws@usace.army.mil) by April 21, 2026, 2:00 PM CT. Use subject line "W912EE26S0004 Industry Day – Yazoo Backwater Pumping Plant".
  • Set-Aside: None specified for this Industry Day.
  • NAICS: 237990 - Other Heavy and Civil Engineering Construction.
  • SAM Registration: Required for all interested firms.

People

Points of Contact

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 5Viewing
Special Notice
Posted: May 5, 2026
Version 4
Special Notice
Posted: Apr 23, 2026
View
Version 3
Special Notice
Posted: Apr 2, 2026
View
Version 2
Special Notice
Posted: Mar 31, 2026
View
Version 1
Special Notice
Posted: Mar 30, 2026
View
Yazoo Backwater Pumping Plant - Industry Day No. 1 | GovScope