Z--Rehab Power and Cooling Systems, Pinnacles NP

SOL #: 140P8426R0002Pre-Solicitation

Overview

Buyer

Interior
National Park Service
PWR PORE MABO (84000)
POINT REYES STATION, CA, 94956, United States

Place of Performance

Paicines, CA

NAICS

Electrical Contractors and Other Wiring Installation Contractors (238210)

PSC

Maintenance Of Miscellaneous Buildings (Z1JZ)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Apr 7, 2026

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The National Park Service (NPS) at Pinnacles National Park (PINN) is seeking proposals for the rehabilitation of power and cooling systems at the West Side Visitor Center in Paicines, CA. This project addresses critical deficiencies in the existing photovoltaic and cooling infrastructure, which currently fail to meet the park's energy demands and climate control needs, posing health and safety risks to visitors and staff. This is a Total Small Business Set-Aside with an anticipated project value between $1,000,000 and $2,000,000. The Request for Proposal (RFP) is expected on or about April 22, 2026.

Scope of Work

The project involves comprehensive upgrades to ensure reliable power and climate control. Key deliverables include:

  • Power System: Installation of a new backup liquid propane generator, a rooftop photovoltaic power system with Unistrut mounting, inverters, battery and PV combiner panels, and associated appurtenances.
  • Chiller System: Rehabilitation including hangers, supports, vibration and seismic controls, testing, adjusting, balancing, piping insulation, commissioning, hydronic piping, and air-cooled, scroll water chillers.
  • Electrical: Installation of low-voltage and control-voltage power conductors and cables, grounding, bonding, conduits, underground ducts, panelboards, fuses, enclosed switches, circuit breakers, photovoltaic collectors, and gas-engine-driven generator sets.
  • Civil: Associated concrete work, rebar, earth moving, stripping, grubbing, backfill, and compaction.

Contract & Timeline

  • Contract Type: Single, Firm-Fixed-Price contract.
  • Estimated Value: The government seeks offers between $1,000,000 and $2,000,000, though this is a courtesy figure and not a strict ceiling or floor.
  • Period of Performance: Approximately 6 months, with work anticipated to start July/August 2026 and complete January/February 2027.
  • Set-Aside: This is a Total Small Business Set-Aside.
  • NAICS Code: 238210, Electrical Contractors and Other Wiring Installation Contractors, with a $19 million size standard.
  • RFP Availability: On or about April 22, 2026, exclusively on www.sam.gov.
  • Proposals Due: Approximately 30 days after the RFP is posted.

Evaluation

Award will be made based on a Best Value determination in accordance with FAR Part 15, considering price and factors other than price as detailed in Section M of the solicitation. Offerors must submit both a technical and a business proposal (including price). A Bid Bond in the amount of 20% of the offered price is required.

Additional Notes

  • Site Visit: An organized site visit is scheduled for May 5, 2026, at 11:00 AM (PT) at Pinnacles National Park. Specific meeting details will be provided in the solicitation.
  • Amendments: Offerors are responsible for periodically checking www.sam.gov for any amendments.
  • SAM.gov Registration: An active registration at www.SAM.gov is required by the offer due date for consideration.
  • Questions: All questions must be submitted in writing via email to Phaedra_Fuller@ios.doi.gov and cc: Noha_Buikema@nps.gov, with "140P8426R0002 PINN Power System" in the subject line. Q&A will be compiled and posted as solicitation amendment(s).