Z2DA--Install DDPO per CSR 676-26-702 Tomah
SOL #: 36C77626Q0144Solicitation
Overview
Buyer
Veterans Affairs
Veterans Affairs, Department Of
PCAC (36C776)
INDEPENDENCE, OH, 44131, United States
Place of Performance
Tomah, WI
NAICS
Commercial and Institutional Building Construction (236220)
PSC
Repair Or Alteration Of Hospitals And Infirmaries (Z2DA)
Set Aside
Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14) (SDVOSBC)
Original Source
Timeline
1
Posted
Mar 24, 2026
2
Last Updated
Apr 29, 2026
3
Submission Deadline
Apr 30, 2026, 5:00 PM
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of Veterans Affairs (VA) is soliciting quotes for general construction services to install Data Drop and Power Outlets (DDPO's) as part of the EHRM project at the Tomah VA Medical Center, WI. This is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside with an estimated value between $250,000 and $500,000. Quotes are due April 30, 2026, at 1:00 PM ET.
Scope of Work
This project, identified as Project 676-26-702, requires the contractor to provide all labor, equipment, materials, and supervision for the installation of new DDPO's. Key tasks include:
- Installing new data drops and power outlets.
- Installing fiber cable terminations.
- Pulling new CAT 6A cable for emergency phones.
- Demolishing existing cables (full removal).
- Repairing any damaged ceiling tiles, walls, or paint resulting from installations. The work must comply with detailed technical specifications, drawings, VA standards, and infection control measures (ICRA). Mobile HEPA carts are required for cable pulls in high patient risk areas in specified buildings.
Contract Details
- Contract Type: Firm-Fixed-Price (FFP). No economic price adjustment for labor or materials will be included.
- Period of Performance: 95 calendar days from the Notice to Proceed (NTP), which is anticipated within 90 days after award.
- Set-Aside: 100% Service-Disabled Veteran-Owned Small Business (SDVOSB). Prime contractors must be certified SDVOSBs.
- Estimated Magnitude: $250,000 to $500,000.
Submission & Evaluation
- Quotes Due: April 30, 2026, at 1:00 PM ET.
- Submission: Electronically via email to Bailey Donato (bailey.donato@va.gov) and Sheila M Vickers (sheila.vickers@va.gov).
- Format: Two separate PDF files (Price Quote and Administrative).
- Pricing: Lump sum for Line Item 0001 (Base), in whole dollar values. Prices must be held firm for 90 calendar days.
- Evaluation: Award will be made to the lowest priced offeror whose quote conforms to the solicitation requirements; evaluation is based on price only.
- Amendments: Offerors must acknowledge all amendments. Amendment 0006 incorporated FAR Clause 52.222-90 (Addressing DEI Discrimination by Federal Contractors).
Key Clarifications
- A site visit was held on April 3, 2026.
- Progress payments for stored materials are at the Contracting Officer's discretion.
- Members of the design team are precluded from participating as prime contractors or subcontractors.
- Offerors are responsible for including all state and local sales taxes in their bid.
- Badging and PIV requirements are not needed for this 95-day project.
People
Points of Contact
Bailey DonatoContract SpecialistPRIMARY
Sheila M VickersSECONDARY