R--Stewart Lee Udall Building Door Restoration
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Interior, IBC ACQ SVCS DIRECTORATE, is soliciting quotes for Bronze Door Restoration Services at the Stewart Lee Udall Building. This is a Total Small Business Set-Aside opportunity for a firm-fixed-price contract. The government intends to award based on a Lowest Priced Technically Acceptable (LPTA) basis. Quotes are due by May 11, 2026, at 2:00 PM ET.
Scope of Work
The project involves the cleaning, polishing, and sealing of historic bronze doors, thresholds, handrails, and star accents at the Stewart Lee Udall Building. Specific tasks include:
- Cleaning, polishing, and sealing 10 interior and exterior door thresholds.
- Cleaning and polishing interior handrails, exterior door handles, and star accents on 5 sets (10 door leaves) of patinated doors.
- Sealing both sides of patinated doors and polished star accents.
- Option 1: Cleaning, polishing, and sealing 5 sets (10 door leaves) of interior polished metal doors (door leaves only).
- Option 2: Cleaning, polishing, and sealing 5 sets (10 door leaves) of interior polished metal doors (door leaves only) and 10 door thresholds. Also, cleaning the interior side of 5 sets (10 door leaves) of patinated exterior doors and surrounding framework up to the transom. All work must adhere to GSA Specification for Cleaning and applying protective coatings to bronze architectural elements, updated 2/27/2026, using specified materials. Contractors must develop and implement a Quality Control Plan (QCP) and a Contract-specific Health and Safety Plan (HASP).
Contract Details
- Contract Type: Firm-fixed-price.
- Period of Performance: May 15, 2026, to June 30, 2026.
- Set-Aside: Total Small Business Set-Aside (FAR 19.5).
- NAICS Code: 23850 (Finish Carpentry Contractors) with a Small Business Size Standard of $19 Million.
- Applicable Law: The Service Contract Act applies; refer to FAR 52.222-24 for the latest Wage Determination.
Submission & Evaluation
- Submission Deadline: Quotes must be received by May 11, 2026, at 2:00 PM ET.
- Submission Method: Electronically via email to Xanthe Otterstedt (xanthe_otterstedt@ibc.doi.gov) and Haider Al Azzawi.
- Quote Format: Microsoft Word, Excel, or PDF. Submissions must include a completed SF1449, a projected schedule, an understanding of requirements, Performance Work Statement acknowledgment, and total price.
- Evaluation Criteria: Lowest Priced Technically Acceptable (LPTA), considering Technical Capability and Price.
- Site Visit: An organized site visit was scheduled for April 28, 2026, at 1:00 PM ET. Offerors were required to attend an onsite walk-through.
Additional Notes
Work must be accomplished on weekends, and parking will not be provided. No bid bond or P&P bonds are required. The Performance Work Statement (PWS) has been updated, and answers to industry questions have been provided.