Building FC65 Exhaust System Repairs

SOL #: N4008526R9023Combined Synopsis/Solicitation

Overview

Buyer

Dept Of Defense
Dept Of The Navy
NAVFACSYSCOM MID-ATLANTIC
NORFOLK, VA, 23511-0395, United States

Place of Performance

Camp Lejeune, NC

NAICS

Commercial and Institutional Building Construction (236220)

PSC

Repair Or Alteration Of Miscellaneous Buildings (Z2JZ)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Mar 18, 2026
2
Last Updated
Apr 13, 2026
3
Submission Deadline
Apr 23, 2026, 7:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of the Navy, NAVFACSYSCOM MID-ATLANTIC, is soliciting proposals for Building FC65 Exhaust System Repairs at MCB Camp Lejeune, North Carolina. This project, identified as No. 25-0014, aims to replace the exhaust system and associated ductwork on three dishwashers in Building FC65 to prevent condensation. This is a Total Small Business Set-Aside, but only specific Mechanical MACC Contractors are eligible to submit proposals.

Scope of Work

The primary objective is to replace the existing exhaust system for three dishwashers in Building FC65. Key tasks include:

  • Demolition of existing exhaust fans (F-12, F-7, F-11, F-6), ductwork, wiring, and conduit.
  • Installation of new, properly sized, sloped stainless-steel ductwork with welded seams.
  • Installation of new, properly sized wall-mounted exhaust fans with backdraft dampers.
  • Installation of new circuit breakers, electrical wiring/conduit, and new lockable disconnects in NEMA 4 enclosures.
  • Routing new wiring from disconnects to exhaust fans and installing control wiring to connect dishwashers to new exhaust fans and the Building Management System (BMS).
  • Ensuring new exhaust fans run for an additional 5 minutes after dishwasher shutoff.
  • Sealing areas where ductwork and conduit exit the building.
  • Specific work for F-12 includes prepping and painting new sheetrock ceiling and installing a new access door. For F-6, a temporary wall must be installed in the storage room.

Contract Details

  • Estimated Cost Range: Between $500,000 and $1,000,000.
  • Contract Type: Award based on Lowest Price.
  • Period of Performance: 180 days after award.
  • Funding: Offerors are advised that funding may not be available, and no award will be made if funds are not secured.

Submission & Evaluation

  • Eligibility: This opportunity is restricted to Mechworks Mechanical Contractors, Inc.; North State Mechanical, Inc.; and R&W Construction Company, Inc.
  • Basis for Award: Lowest Price.
  • Proposal Acceptance Period: 60 days from receipt of offers.

Key Dates & Contacts

Special Notes

Work will be performed between 2000 – 0400 (after-hours) to prevent Mess Hall service interruptions, as Building FC65 operates 7 days per week. All scheduling and access must be coordinated with the Building Manager. Offerors must acknowledge receipt of Amendment 0001.

People

Points of Contact

Lauren LocontoSECONDARY

Files

Files

Download
Download
Download
Download
Download
Download

Versions

Version 2Viewing
Combined Synopsis/Solicitation
Posted: Apr 13, 2026
Version 1
Combined Synopsis/Solicitation
Posted: Mar 18, 2026
View