Comanche Park Campground Reconstruction

SOL #: 1240LT26Q0046Combined Synopsis/Solicitation

Overview

Buyer

Agriculture
Forest Service
Black Hills National Forest
CUSTER, SD, 57730, United States

Place of Performance

Custer, SD

NAICS

Water and Sewer Line and Related Structures Construction (237110)

PSC

Construction Of Water Supply Facilities (Y1NE)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Apr 10, 2026
2
Last Updated
May 7, 2026
3
Submission Deadline
May 11, 2026, 5:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The USDA Forest Service, Black Hills National Forest, is soliciting proposals for the Comanche Park Campground Reconstruction project in Custer, SD. This Total Small Business Set-Aside opportunity involves significant upgrades to expand the campground from 20 to 34 sites, modernize infrastructure, and improve visitor facilities. Proposals are due May 11, 2026, at 12:00 PM Central Time.

Scope of Work

The contractor will provide all labor, materials, and equipment for comprehensive campground improvements. Key tasks include:

  • Expanding the campground from 20 to 34 sites.
  • Modifying and resurfacing existing roads, including curve widening and drainage shaping.
  • Relocating and upgrading the Host Site and Volunteer Site with new power, water, and wastewater vaults.
  • Replacing five original 1965 stick-built toilets with four new pre-cast vault toilets.
  • Decommissioning the existing pumphouse and installing a new pre-cast concrete treatment building with upgraded plumbing and controls.
  • Removing the existing aboveground water storage tank and installing a new 3,000-gallon below-ground fiberglass water storage tank.
  • Replacing all water distribution piping and installing new hydrants.
  • The project may also include new trails connecting the campground to a nearby motorized trail system.

Contract Details

  • Contract Type: Firm Fixed Price
  • Magnitude of Construction: Between $1,000,000 and $5,000,000
  • Period of Performance: 392 days from the Notice to Proceed (NTP). On-site work is anticipated to begin in late summer to early fall.
  • Set-Aside: Total Small Business Set-Aside (FAR 19.5)
  • NAICS Code: 237110 - Water and Sewer Line and Related Structures Construction (Small Business Size Standard: $45M)
  • Place of Performance: Comanche Park Campground, 6.5 miles west of Custer, SD.

Key Clarifications & Updates

Recent Q&A documents have provided important clarifications:

  • Option Items: All option items have been removed from the contract.
  • Signs/Gates: Signs and the road closure gate shown on plan drawing sheet C8.1 are eliminated.
  • Phasing: The project does not require phasing; the entire campground will be closed for aggressive completion.
  • Electrical Service: A new electrical service is required, and the contractor is responsible for payments to the power company for their services.
  • Water: Bulk water for grading is the contractor's responsibility.
  • Environmental: Contractors must immediately report any dead or injured bats. No asbestos or lead paint is present. An SWPPP is required, and erosion control pricing should be included in Base Item #1.
  • Permitting: All state and county permits are required.

Submission & Evaluation

  • Quotations Due: May 11, 2026, at 12:00 PM Central Time.
  • Submission Method: Via email to Erick Plamann (erick.plamann@usda.gov).
  • Required Documents: Experience/Past Performance (max 3 pages), Written Technical Approach (2-4 pages) including three similar projects, Attachment 1- SOI, and Signed SF-30 (if applicable).
  • Evaluation Factors: Comparative evaluation based on Experience/Past Performance, Technical Approach, and Price. Award will be made to the offeror providing the best value, not necessarily the lowest price.

Site Visit

An organized site visit was held on April 17, 2026, at 9:00 AM Mountain Time at Comanche Park Campground.

People

Points of Contact

Erick PlamannPRIMARY
Lucas DahlmanSECONDARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 4Viewing
Combined Synopsis/Solicitation
Posted: May 7, 2026
Version 3
Combined Synopsis/Solicitation
Posted: Apr 28, 2026
View
Version 2
Combined Synopsis/Solicitation
Posted: Apr 27, 2026
View
Version 1
Combined Synopsis/Solicitation
Posted: Apr 10, 2026
View