Construct Vehicle Maintenance Shop (VMS) at Bakersfield
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
The USPFO for California intends to award a single firm-fixed-price contract for non-personal construction services, to include all plant, labor, transportation, materials, tools, equipment, appliances, permits, and supervision necessary for the construction of a 24,564 SQFT National Guard Vehicle Maintenance Shop (VMS) at the Bakersfield Army National Guard Readiness Center (Gateway Ave.), Kern County, California. Integral characteristics/items of the VMS include Backup/Emergency Generator, Organizational Vehicle Parking (Paved), Controlled Waste Facility, Flammable Materials Facility, and Electric Power, Photovoltaic. This project will include comprehensive interior design. This facility will be designed to meet Industry Standards as well as all local, State, and Federal building codes and as per Public Law 90-480. Construction will include all utility services, information systems, fire detection and alarm systems, cranes, roads, walks, curbs, gutters, storm drainage, parking areas for approximately 20 privately owned vehicles and site improvements.
Update - 25 May 2025
The pre-bid conference slides, sign-in sheet, and minutes have been posted. Additionally, Round 1 of RFIs has been posted.
Update - 30 May 2025
Amendment 001 was issued in order to formally incorporate "Type B 100% Bid Final Design Report Volume 1" which includes the geotechnical survey at "Appendix B". Note that this document has been redacted to remove brand names and the Government's cost estimate. Additionally, Round 2 of RFIs has been posted.