Fort Peck Hydraulic Vertical Pivot Gate

SOL #: W9128F26QA029Combined Synopsis/Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W071 ENDIST OMAHA
OMAHA, NE, 68102-4901, United States

Place of Performance

Fort Peck, MT

NAICS

All Other Specialty Trade Contractors (238990)

PSC

Repair Or Alteration Of Miscellaneous Buildings (Z2JZ)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Mar 19, 2026
2
Last Updated
Mar 19, 2026
3
Submission Deadline
Apr 17, 2026, 7:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The US Army Corps of Engineers (USACE) Omaha District is soliciting proposals for the Fort Peck Hydraulic Vertical Pivot Gate project (Solicitation W9128F26QA029). This Total Small Business Set-Aside opportunity involves the procurement and installation of a new hydraulic vertical pivot gate to replace an existing double swing gate at the Fort Peck Outside Maintenance Facility in Fort Peck, Montana. The estimated value for this Firm Fixed-Price contract is between $100,000 and $250,000. Proposals are due by April 17, 2026, at 2:00 PM CT.

Scope of Work

The project requires furnishing and installing a complete Hydraulic Vertical Pivot Gate system and associated appurtenances to enhance equipment security and force protection. Key components include a hydraulic power unit, electrical system, and barrier system (steel or aluminum, up to 25 ft opening). The scope also covers additional features such as a cold weather package, radio controls, detector system, reversing edge, magnetic lock, photo eye, and access control via key switches and pedestals with card readers. The contractor will also be responsible for removing and reinstalling an existing entrance gate to a specified location. All work must comply with USACE Engineering Manual (EM) 385-1-1, OSHA standards, environmental regulations, and the E-Verify program. A Contractor Quality Control (CQC) program is required.

Contract Details & Timeline

  • Contract Type: Firm Fixed Price
  • Period of Performance: 365 calendar days after Notice to Proceed (anticipated May 1, 2026, to April 30, 2027)
  • Estimated Value: $100,000.00 to $250,000.00
  • Set-Aside: Total Small Business Set-Aside (FAR 19.5)
  • NAICS Code: 238990 (Small Business Size Standard: $19,000,000)
  • Proposal Due: April 17, 2026, by 2:00 PM CT
  • Questions Due: March 31, 2026, by COB
  • Answers Posted: April 2, 2026, by COB on SAM.gov
  • Site Visit: March 31, 2026, at 10:00 AM CT, Fort Peck Administration Office. Attendees must contact the POC.

Submission & Evaluation

Proposals should be submitted to the COE FT PECK PROJECT OFFICE. Evaluation will be based on a Best Value Tradeoff, with Technical Capability and Past Performance being more important than Price. Offerors must be registered in SAM.gov and acknowledge Amendment 0001 with their offer. The price schedule includes CLINs for furnishing the gate, labor & equipment, and mobilization/demobilization. Wage determinations for Valley and McCone Counties, Montana, apply.

Points of Contact

People

Points of Contact

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 3Viewing
Combined Synopsis/Solicitation
Posted: Mar 19, 2026
Version 2
Combined Synopsis/Solicitation
Posted: Mar 19, 2026
View
Version 1
Combined Synopsis/Solicitation
Posted: Mar 19, 2026
View
Fort Peck Hydraulic Vertical Pivot Gate | GovScope