FY26: STATION (PROJ: 548-26-103) BB OR Sub-sterile Rooms Cabinets Removal Replacement

SOL #: 36C24826Q0241Combined Synopsis/Solicitation

Overview

Buyer

Veterans Affairs
Veterans Affairs, Department Of
248-NETWORK CONTRACT OFFICE 8 (36C248)
TAMPA, FL, 33637, United States

Place of Performance

West Palm Beach, FL

NAICS

Commercial and Institutional Building Construction (236220)

PSC

Maintenance Of Hospitals And Infirmaries (Z1DA)

Set Aside

Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14) (SDVOSBC)

Timeline

1
Posted
Jan 16, 2026
2
Last Updated
Feb 26, 2026
3
Submission Deadline
Feb 13, 2026, 3:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of Veterans Affairs (VA) is soliciting proposals for project 548-26-103, which involves the removal and replacement of cabinets and flooring in the OR Sub-sterile Rooms at the West Palm Beach VA Medical Center in Florida. This is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside. Proposals are due February 13, 2026.

Scope of Work

The contractor will provide all labor, materials, and equipment to renovate OR Sub-sterile Rooms 2A-211A and S1-207A. Key tasks include:

  • Demolition: Removal of existing vinyl flooring, bottom/top cabinets, a large sink, abandoned steam sterilizers, and built-in blanket/fluid warmers.
  • Installation: New stainless steel cabinets (equal or greater quality), two electrical receptacles, and seamless welded vinyl flooring with integrated cove base.
  • Facility Maintenance: Capping of steam lines, wall repairs (caulking, mudding, epoxy painting), and maintaining negative pressure containment throughout the project.

Contract & Timeline

  • Contract Type: Firm-Fixed-Price (FFP)
  • Magnitude of Construction: Between $250,000 and $500,000
  • Period of Performance: 90 calendar days from Notice to Proceed (NTP)
  • Set-Aside: 100% SDVOSB
  • Proposal Due Date: February 13, 2026, at 10:00 AM EST
  • RFI Deadline: January 26, 2026, at 10:00 AM EST

Evaluation

Award will be made on a trade-off basis, where technical factors are significantly more important than price. Evaluation factors include:

  1. Technical Approach
  2. Schedule
  3. Past Performance

Additional Notes

Amendment 1 was issued on January 23, 2026, to provide the site visit sign-in sheet. Contractors must be registered in SAM and the SBA Veteran Small Business Certification (VetCert) database. A 20% bid guarantee and 100% payment/performance bonds are required.

People

Points of Contact

Stacy FiglinskiPRIMARY

Files

Files

Download

Versions

Version 3
Combined Synopsis/Solicitation
Posted: Feb 26, 2026
View
Version 2Viewing
Combined Synopsis/Solicitation
Posted: Jan 23, 2026
Version 1
Combined Synopsis/Solicitation
Posted: Jan 16, 2026
View
FY26: STATION (PROJ: 548-26-103) BB OR Sub-sterile Rooms Cabinets Removal Replacement | GovScope