Generator Semi-Annual Preventive Maintenance (PM), Emergency Repair Services (ERS)
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
ADDENDUM #2 1/8/26
An updated Combined Synopsis has been posted.
END
ADDENDUM #1 1/6/26
RFI #1
1. Could you please confirm whether this is a new requirement? If not, we kindly request the incumbent contractor’s name and the previous contract number.
a. This action is a follow-on requirement
Contract number: W91QF0-21-P-0040
Contract Awardee: Virginia Energy & Lighting, LLC.
Description of requirement: Caterpillar Diesel Standby Generator Preventive Maintenance (PM) and Emergency Repair Services (ERS)
Method of procurement: Set-Aside Small Business
Contract type: Firm-Fixed Price
Number of option periods: 4
2. Additionally, are there any notable changes to the scope of work compared to the prior award?
a. The scope of the contract has changed significantly since the previous award. Key additions include annual Advantage Extended Service Coverage (ESC) certification inspection, load bank testing, battery replacement, consumable parts replacement, and fluid sampling and testing services. These enhancements were introduced to address the requirements brought about by upgraded equipment, improved maintenance procedures, the need for additional coverage for new assets, and expanded preventive maintenance services. Incorporating fluid sampling also helps prevent equiopment damage, making the new contract more comprehensive and cost-effective by consolidating service that were previously sourced separately at higher expense.
END
This is to confirm that the site visit for the requirement is scheduled for January 7, 2026, at 0900 AM. Please confirm by email to Myrisha Mullen @ myrisha.l.mullen2.civ@army.mil, if you will be in attendance.
Please find attached the following documents for your reference:
- Performance Work Statement (PWS)
- Combined Synopsis
- CLIN Structure
Additionally, please note that the deadline for submitting questions is January 9, 2026, at 1500 PM.