Generator Semi-Annual Preventive Maintenance (PM), Emergency Repair Services (ERS)

SOL #: W91QF526RA002Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W6QM MICC FT LEE
FORT LEE, VA, 23801, United States

Place of Performance

Radford, VA

NAICS

Electrical Contractors and Other Wiring Installation Contractors (238210)

PSC

Maintenance, Repair And Rebuilding Of Equipment: Mechanical Power Transmission Equipment (J030)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Dec 17, 2025
2
Last Updated
Jan 9, 2026
3
Submission Deadline
Jan 19, 2026, 8:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

ADDENDUM #3 1/9/26

RFI #2

1. Is the 2 hour on site requirement for Emergence call a must have?

       a. Yes.   These are back-up generators that need to be operational within 2hrs or less as IT equipment switches to battery back-up which only lasts for a very short time with the heavy data center load.  

2. Can you clarify the Testing requirements for the Load Banking of each generator ? Load Percentages and time for each level

       a. This is outlined within PWS para 4.1.5.1
                  i. 30 minutes at 20% of rated load of genset.
                 ii. 30 minutes at 50% of rated load of genset.

3. Are there different requirements for each generator?

       a. No, generators are all Caterpillar and follow the same type of load bank testing.

4. How often does the Load Testing happen, and what time of year?

       a. This is outlined with PWS para 4.1.5.1 

               i. Annual load bank test

5. Doing the Advantage ESC, witch CAT Dealership does the report get sent to?

        a. Once the vendor performs services, they return to their office to finalize the service and send a copy to our facilities management team and the COR.  This action usually takes them less than 2-3 days (depending on workload)

END

ADDENDUM #2 1/8/26

An updated Combined Synopsis has been posted.

END

ADDENDUM #1 1/6/26

RFI #1

1. Could you please confirm whether this is a new requirement? If not, we kindly request the incumbent contractor’s name and the previous contract number.

            a. This action is a follow-on requirement

Contract number:  W91QF0-21-P-0040
Contract Awardee:  Virginia Energy & Lighting, LLC.
Description of requirement:  Caterpillar Diesel Standby Generator Preventive Maintenance (PM) and Emergency Repair Services (ERS)
Method of procurement:  Set-Aside Small Business
Contract type:  Firm-Fixed Price
Number of option periods:  4

2. Additionally, are there any notable changes to the scope of work compared to the prior award?

      a. The scope of the contract has changed significantly since the previous award. Key additions include annual Advantage Extended Service Coverage (ESC) certification inspection, load bank testing, battery replacement, consumable parts replacement, and fluid sampling and testing services. These enhancements were introduced to address the requirements brought about by upgraded equipment, improved maintenance procedures, the need for additional coverage for new assets, and expanded preventive maintenance services. Incorporating fluid sampling also helps prevent equiopment  damage, making the new contract more comprehensive and cost-effective by consolidating service that were previously sourced separately at higher expense.

END

This is to confirm that the site visit for the requirement is scheduled for January 7, 2026, at 0900 AM. Please confirm by email to Myrisha Mullen @ myrisha.l.mullen2.civ@army.mil, if you will be in attendance. 

Please find attached the following documents for your reference:

  • Performance Work Statement (PWS)
  • Combined Synopsis
  • CLIN Structure

Additionally, please note that the deadline for submitting questions is January 9, 2026, at 1500 PM. 

People

Points of Contact

Myrisha L. MullenPRIMARY
Octavia Heflin-SmithSECONDARY

Files

Files

Download
Download
Download
Download

Versions

Version 4Viewing
Solicitation
Posted: Jan 9, 2026
Version 3
Solicitation
Posted: Jan 8, 2026
View
Version 2
Solicitation
Posted: Jan 6, 2026
View
Version 1
Solicitation
Posted: Dec 17, 2025
View
Generator Semi-Annual Preventive Maintenance (PM), Emergency Repair Services (ERS) | GovScope