ID FLAP FS SC MULTI(1), Custer Motorway Stabilization Project

SOL #: 69056725R000008Solicitation

Overview

Buyer

Transportation
Federal Highway Administration
690567 WESTERN FEDERAL LANDS DIV
VANCOUVER, WA, 98661, United States

Place of Performance

Challis, ID

NAICS

Highway (237310)

PSC

Construction Of Highways, Roads, Streets, Bridges, And Railways (Y1LB)

Set Aside

No set aside specified

Timeline

1
Posted
Aug 20, 2025
2
Last Updated
Jan 21, 2026
3
Submission Deadline
Jan 29, 2026, 10:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Federal Highway Administration (FHWA), under the Department of Transportation, is soliciting proposals for the Custer Motorway Stabilization Project (Solicitation No. 69056725R000008) in Challis, ID. This is a Firm Fixed-Price Task Order Contract under the existing Idaho, Montana, and Surrounding Areas Multiple Award Task Order Contract (MATOC) IDIQ. The project is estimated to be between $700,000 and $2,000,000. Proposals are due January 29, 2026.

Scope of Work

This project involves bank stabilization, reinforced soil slope construction, and roadway resurfacing at two sites along the Custer Motorway (Mile Post 24.0 and Mile Post 25.3) within the Salmon-Challis National Forest. The work addresses erosion and shallow slope failures caused by Mill Creek scour. Key deliverables include:

  • Construction of Reinforced Soil Slopes (RSS) over riprap revetment.
  • Bank stabilization using buried log revetments, root wads, and fish passage boulders.
  • Temporary stream diversion, erosion control, and planting.
  • Implementation of temporary traffic control measures.

The project is divided into two bid schedules:

  • Schedule A: Focuses on work at MP 25.3 (0.04 miles).
  • Schedule B: Includes all work from Schedule A plus additional work at MP 24.0 (0.10 miles).

Contract & Timeline

  • Contract Type: Firm Fixed-Price Task Order Contract.
  • Estimated Value: $700,000 to $2,000,000.
  • Period of Performance: Schedule A completion by July 22, 2026; Schedule B completion by October 29, 2026. Notice to Proceed expected March 23, 2026.
  • Proposal Due Date: January 29, 2026.
  • Questions Due: January 22, 2026.

Eligibility & Evaluation

This solicitation is restricted to existing IDIQ holders under the Idaho, Montana, and Surrounding Areas MATOC. Proposals will be evaluated based on lowest price. Large businesses must submit an acceptable subcontracting plan prior to award. A bid bond is required.

Key Updates & Notes

  • Amendment A001 (Jan 13, 2026): Updated the Davis-Bacon General Wage Decision Number to ID20260078 and revised sections on electronic documentation, Masterworks, Contractor's Daily Record, Measurement of Work, Pricing Adjustments, and Progress Payments. The proposal due date was not extended.
  • Q&A (Jan 20, 2026): Clarified that bidders must provide pricing for both Schedule A and Schedule B, but only one schedule will ultimately be awarded.
  • Printed proposals are required; electronic bids are not accepted. Offerors must acknowledge Amendment A001 with their offer.
  • Site viewing may be difficult due to snow; no show-me tours will be available.

People

Points of Contact

Contracts G. OfficePRIMARY

Files

Files

Download
Download
Download

Versions

Version 4
Solicitation
Posted: Jan 21, 2026
View
Version 3
Solicitation
Posted: Jan 14, 2026
View
Version 2Viewing
Solicitation
Posted: Dec 29, 2025
Version 1
Pre-Solicitation
Posted: Aug 20, 2025
View
ID FLAP FS SC MULTI(1), Custer Motorway Stabilization Project | GovScope