LCLS-II-HE EI Process Cooling Water (PCW) Skid Equipment Fabrication
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of Energy's SLAC National Accelerator Laboratory is soliciting firm-fixed-price proposals for the LCLS-II-HE EI Process Cooling Water (PCW) Skid Equipment Fabrication. This opportunity involves providing a complete, factory-assembled PCW Skid Assembly to replace an existing unit in Building 950A in Menlo Park, CA, aiming to enhance cooling reliability and efficiency. Proposals are due Tuesday, February 3, 2026, at 5:00 PM PST.
Scope of Work
The requirement is for one (1) complete, skid-mounted mechanical package including dual circulation pumps, a heat exchanger, expansion tank, air separator, filtration assembly, instrumentation, controls, and electrical components. The design and fabrication must comply with SLAC technical standards, ASME B31.3, NFPA 70, and applicable UL and ANSI codes. All wetted materials must be non-corrosive and compatible with SLAC's process cooling water chemistry. A Factory Acceptance Test (FAT) is required before shipment. SLAC will perform installation, utility tie-ins, and commissioning.
Detailed technical specifications, as outlined in the Bulletin 4 Drawings, include:
- Pipe Installation: Materials like Copper Type L, 316L Stainless Steel, and Schedule 40 Black Steel for various piping systems (PCWS/R, CHWS/R, Makeup Water).
- Pressure Testing: Specific requirements for test mediums, pressures, and durations.
- Equipment Schedules: Detailed specifications for new pumps (B950A-PCWP-1001/1002), heat exchanger (B950A-HX-PCWP-1001), Variable Frequency Drives (VFDs), and a water filter (B950A-WF-1001).
Contract & Timeline
- Contract Type: Firm-Fixed-Price Subcontract.
- Period of Performance: To be mutually agreed upon, commencing upon subcontract award.
- Set-Aside: None specified.
- Proposal Submission Deadline: Tuesday, February 3, 2026, 5:00 PM PST.
- Offeror Questions Deadline: Wednesday, January 28, 2026, 5:00 PM PST.
- Proposal Validity: 90 days after submission.
- Published Date: January 22, 2026.
Evaluation & Submission
Award will be based on a Lowest Price, Technically Acceptable (LTPA) evaluation method. Technical proposals will be assessed on a "Meets Requirements" or "Does Not Meet Requirements" basis, considering ability to meet technical requirements, schedule, past performance, warranty, and facilities. Business proposals will be evaluated on financial standing and price.
Proposals must be submitted electronically in PDF format. Offerors must be registered with the System for Award Management (SAM). Contact Ryan Hodges (rhodges@slac.stanford.edu, 650-926-3464) for access to all technical documentation.