Lowell National Historical Park - REPLACE COOLING
SOL #: 140P4326R0020Solicitation
Overview
Buyer
Interior
National Park Service
NER SERVICES MABO (43000)
BOSTON, MA, 02108, United States
Place of Performance
Lowell, MA
NAICS
Plumbing (238220)
PSC
Repair Or Alteration Of Museums And Exhibition Buildings (Z2JA)
Set Aside
Total Small Business Set-Aside (FAR 19.5) (SBA)
Original Source
Timeline
1
Posted
Apr 28, 2026
2
Submission Deadline
Jun 10, 2026, 4:00 PM
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The National Park Service is soliciting proposals for a Firm Fixed-Price construction project to replace Cooling Tower #1 and associated pumps at Lowell National Historical Park, MA. This requirement is a Total Small Business Set-Aside with an estimated magnitude between $250,000 and $500,000. Proposals are due June 10, 2026.
Project Scope
This project involves the replacement of critical HVAC infrastructure at the Boott Cotton Mill #6. The primary scope includes:
- Cooling Tower Replacement: Removal of the existing rooftop cooling tower and installation of a new low-rise cooling tower on vibration rails, including piping connections and valve replacement.
- Pump Replacement: Replacement of one 384 gpm condenser pump and two 500 gpm circulatory pumps, with the addition of Variable Frequency Drives (VFDs).
- Valve and Piping Replacement: Replacement of approximately 24 ball valves, flexible joints, 1 automatic control valve, 4 butterfly valves, and about 16 linear feet of pipe and connections.
- System Integration: Programming new equipment to the Trane Building Management System.
- Electrical Work: Installation of new conduit and wiring for new motors.
- Optional Work: Replacement of an additional circulatory pump in an adjacent building's basement mechanical room, including VFD, valves, piping, and BMS integration.
Contract Details
- Contract Type: Firm Fixed Price
- Set-Aside: Total Small Business Set-Aside (FAR 19.5)
- Estimated Magnitude: $250,000.00 - $500,000.00
- Period of Performance: October 15, 2026, to September 30, 2027 (350 calendar days after Notice to Proceed).
- Place of Performance: Boott Cotton Mill #6, Lowell, MA.
- Wage Determination: Davis-Bacon Wage Determination MA20260001 applies, specifying prevailing wage rates and fringe benefits for various labor categories in Massachusetts counties, which must be factored into cost proposals.
- Contract Administration: Bidders should review FAR 36.211(b) regarding policies and procedures for definitizing equitable adjustments for change orders.
Submission & Evaluation
- Proposal Submission Deadline: June 10, 2026, by 12:00 PM local time.
- Submission Method: Proposals must be submitted via email to Samuel_McKenzie@ios.doi.gov.
- Evaluation Process: Best Value Continuum Tradeoff Process.
- Key Evaluation Factors: Technical Approach, Project Experience, Training, and Price.
- Site Visit: A site visit is scheduled for May 6, 2026, at 1:00 PM ET at 115 John St, Lowell, MA. Attendance is highly recommended.
Contact Information
- Primary Contact: Samuel McKenzie (samuel_mckenzie@nps.gov)
People
Points of Contact
McKenzie, SamuelPRIMARY
Files
Versions
Version 1Viewing
Solicitation