Y--Montezuma NWR New Multipurpose Facility
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The U.S. Fish and Wildlife Service (FWS), under the Department of Interior, is soliciting proposals for the construction of a New Multipurpose Facility at the Montezuma National Wildlife Refuge (NWR) & NY Ecological Services. This opportunity, identified as Solicitation 140FGA26R0006, is a Total Small Business Set-Aside. Proposals are due by April 20, 2026, at 1400 local time.
Scope of Work
The project primarily involves Base Building Multi-Purpose Facility Construction. Additionally, it includes four additive items: Resurfacing Parking Area MUP, PV system S Roof MNT, PV System N Roof MNT, and Furniture MNT. Detailed specifications have been provided for various components, including:
- Self-adhering sheet waterproofing for vertical and horizontal applications (Specification Section 07 13 16).
- Ground-set flagpoles (Specification Section 10 75 16), detailing materials, fabrication, and installation.
- Specific requirements for flooring, sound absorbing wall units, emulsified asphalt coating, electric locks, HVAC system connection, and ADA restroom grab bar heights.
Contract Details
This is a Solicitation for construction services. The anticipated performance period for the base construction and all additives is from June 1, 2026, to November 30, 2027, requiring completion within 548 calendar days after receiving notice to proceed. Performance and payment bonds are mandatory. Funding for this contract is contingent upon the availability of appropriated funds.
Submission Requirements
Offers must be submitted by April 20, 2026, at 1400 local time. Submissions require an original and one copy, marked with the offeror's name, address, solicitation number, and due date/time, in sealed envelopes. Offers providing less than 60 calendar days for Government acceptance will be rejected. All questions must be submitted via email to Ian_a_young@fws.gov. Bidders must acknowledge receipt of all amendments.
Key Clarifications & Technical Details
Recent amendments and Q&A documents have provided critical clarifications:
- Prevailing wages apply to laborers and mechanics employed "on the site of the work," specifically for labor involved in securing systems furniture to the building.
- The contractor is responsible for directly paying for all required testing and inspections, including Special Inspections, and must include these costs in the lump sum bid.
- Steel pile load testing requires Dynamic Load Testing (PDA testing) with signal matching analysis (CAPWAP), including both end-of-driving and restrike testing, calibrated against at least one Static Load Test, targeting a minimum Factor of Safety (FS) of 2.0.
- Geotechnical reports (2303568_FINAL_MNWR_Geotech_Report_R1-Nov2024 and 21003122A_-Montezuma_NWR-_Geotechnical_Report_Sealed) are available as attachments to Amendment 0001, providing detailed subsurface conditions and foundation recommendations.