TINKER AFB MAC BOA WWYK250013 - Renovate to Open Storage B1115

SOL #: FA813726R0022Combined Synopsis/Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Air Force
FA8137 AFSC PZIOC
TINKER AFB, OK, 73145-9125, United States

Place of Performance

S Coffeyville, OK

NAICS

Commercial and Institutional Building Construction (236220)

PSC

Repair Or Alteration Of Office Buildings (Z2AA)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Apr 24, 2026
2
Last Updated
Jun 12, 2026
3
Submission Deadline
Jun 17, 2026, 5:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of the Air Force (FA8137 AFSC PZIOC) is soliciting proposals for the TINKER AFB MAC BOA WWYK250013 - Renovate to Open Storage B1115 project. This opportunity is a Total Small Business Set-Aside and is exclusively open to Tinker AFB MAC BOA Holders who attended the mandatory site visit on May 13, 2026. The project involves renovating Room 8, Building 1115, into an open storage room at Tinker Air Force Base, Oklahoma. Requests for Information (RFIs) are due by May 20, 2026, 5:00 PM CST, and proposals are due by June 17, 2026, 5:00 PM CST.

Scope of Work

The contractor will provide all necessary design/engineering services, materials, labor, and equipment to renovate Room 8, B1115, into an open storage room. Key tasks include:

  • Performing a site investigation to verify existing conditions.
  • Identifying and providing all logistical, architectural, and structural work elements.
  • Ensuring complete, fully operating systems and assemblies.
  • Demolition of existing elements (e.g., wood doors, frames, portions of walls).
  • New construction including drywall, insulation, solid core wood doors, and frames.
  • Installation of new electrical components (outlets, communication rough-ins, LED downlights) and demolition of existing electrical systems.

Contract Details

  • Contract Type: Combined Synopsis/Solicitation under a Multiple Award Contract (MAC) BOA.
  • Estimated Value: Between $250,000 and $500,000.
  • Performance Period: Work to commence within 10 calendar days after award, with completion within 207 calendar days after award/notice to proceed.
  • Bonds: Performance and payment bonds are required.
  • Funding: The Government's obligation is contingent upon the availability of appropriated funds.
  • Wage Rates: Prevailing wage rates and fringes for Oklahoma County apply, as detailed in the WWYK250013 Wage Determination Findings.

Eligibility & Submission

  • Set-Aside: Total Small Business Set-Aside (FAR 19.5).
  • Mandatory Requirement: Only MAC BOA Holders who attended the site visit on May 13, 2026, are eligible to propose.
  • RFI Submission: Via email to Contracting Points of Contact by May 20, 2026, 5:00 PM CST.
  • Proposal Submission: Electronic submissions are required, readable by MS Office 2007-2013 or Adobe Acrobat PDF (searchable text). Files must not be password-protected. Proposals must include a completed Order Proposal Request (OPR), amendments, and a cover letter.
  • Format: 8.5 x 11 inches, 1.5 line spacing, minimum Arial 12pt font (Arial 8pt for tables/charts). All pages must be numbered and include the legend "CUI SOURCE SELECTION INFORMATION".
  • Bid Guarantee: A minimum 20% bid guarantee is required.
  • Representations & Certifications: Annual representations and certifications must be completed electronically via SAM.gov.

Evaluation Factors

Award will be made using Lowest Priced Technically Acceptable (LPTA) source selection procedures. Proposals will be evaluated concurrently on technical factors and price.

  • Technical Evaluation (Acceptable/Unacceptable):
    • Subfactor 1: Capability and Management (commitment to on-site team, management approach, warranty handling, points of contact).
    • Subfactor 2: Schedule and Planning (realistic construction schedule, ability to meet or improve mandatory completion dates).
  • Price Evaluation: Assessed for reasonableness, balance, and realism.

Key Personnel Requirements

Key personnel, as outlined in the Statement of Work, include a Project Manager, Design Project Manager (licensed in Oklahoma), Quality Control Manager, Site Safety and Health Officer, and Project Superintendent, each with specific experience requirements.

Key Dates

  • RFI Due Date: May 20, 2026, 5:00 PM CST
  • Proposal Due Date: June 17, 2026, 5:00 PM CST
  • Published Date: May 13, 2026

Contact Information

People

Points of Contact

Dedrian Parmer JrPRIMARY
Stephen PalmerSECONDARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 7
Combined Synopsis/Solicitation
Posted: Jun 12, 2026
View
Version 6
Combined Synopsis/Solicitation
Posted: May 29, 2026
View
Version 5
Combined Synopsis/Solicitation
Posted: May 29, 2026
View
Version 4
Combined Synopsis/Solicitation
Posted: May 22, 2026
View
Version 3Viewing
Combined Synopsis/Solicitation
Posted: May 13, 2026
Version 2
Combined Synopsis/Solicitation
Posted: May 11, 2026
View
Version 1
Combined Synopsis/Solicitation
Posted: Apr 24, 2026
View
TINKER AFB MAC BOA WWYK250013 - Renovate to Open Storage B1115 | GovScope