Y1PZ--Fayetteville National Cemetery, Columbaria and In-ground Cremains Burial Expansion (VA-25-00092710)
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of Veterans Affairs (VA), National Cemetery Administration, is soliciting bids for the Columbaria and In-ground Cremains Burial Expansion project at Fayetteville National Cemetery, AR. This is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside for a Firm, Fixed-Priced construction contract. Bids are due by March 13, 2026, at 10:00 AM EDT.
Scope of Work
This project involves general construction services for the expansion of burial grounds. Key deliverables include:
- CLIN 01: Base Bid for Columbaria and In-ground Cremains Burial Expansion and Sitework.
- CLIN 02: Construction of Administration/PIC/Restroom Building, Material Storage Shelter, Equipment Storage Structure, Committal Shelter, Entrance Gate, Hazmat Storage Enclosure, AST, and Service Building.
- CLIN 03: Roof Replacement. The contractor must provide all labor, materials, tools, equipment, and services in accordance with the provided Statement of Work, Drawings, and Specifications. Adherence to "Dignity Standards" and Historic Compliance is critical.
Contract Details
- Contract Type: Firm, Fixed-Priced (FAR Part 14, Sealed Bidding).
- Project Magnitude: Between $2,000,000 and $5,000,000.
- Performance Period: 545 calendar days (approximately 18 months) from the Notice to Proceed.
- Place of Performance: Fayetteville National Cemetery, 1000 S Lt Col Leroy Pond Ave, Fayetteville, AR 72701.
- NAICS Code: 237990 (Small Business Size Standard $45.0 Million).
- Product Service Code: Y1PZ (Construction Of Other Non Building Facilities).
Site Conditions & Requirements
A geotechnical investigation revealed subsurface conditions including topsoil, flexible asphalt, moisture-sensitive fine-grained soils, and highly weathered to hard shale. Bidders should anticipate potential excavation difficulties and the need for dewatering. Foundation recommendations for shallow foundations are provided, requiring specific bearing depths and compacted fill. Pavement recommendations include mill-and-overlay or full-depth removal. Work must occur during normal operating hours (M-F, 8:00 am – 4:30 pm), cease during ceremonies, and adhere to strict conduct and no-smoking policies. Limited parking requires coordination. Wage Determination AR20260058 applies, establishing prevailing wage rates and fringe benefits.
Submission & Evaluation
- Bids Due: Friday, March 13, 2026, at 10:00 AM EDT.
- Submission Method: Electronically via email to trevor.disimone@va.gov (due to eCMS Vendor Portal issues).
- Required Documents: SF 1442 (Blocks 14-20), Schedule B pricing, "IFB Contractor Cost Estimate Worksheet" (S02_Attachment 5), SF 30 Amendments, and a bid bond.
- Virtual Bid Opening: Information will be transmitted upon RSVP or bid package receipt.
- Site Visit: A sign-in sheet confirms a site visit was held on February 18, 2026.
- Questions: The deadline for questions was February 21, 2025.
Eligibility
This acquisition is 100% set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB). Offerors must be registered in VetCert, VETS-4212, and SAM.
Key Clarifications from Amendment
The amendment clarified that access via Hill Ave requires city coordination, concrete curb depth is 18 inches, grass seed should align with City of Fayetteville standards, stone mulch is 3/4 inch, and City permits will be required. No hazardous materials are associated with the Hazardous Waste Storage Building removal, and the project is under 1 acre, not requiring a stormwater permit. Rock removal specifications may be issued if hard weathered shale is encountered.