A250 Emergency Repairs to Pier 1

SOL #: 140P4326R0001Solicitation

Overview

Buyer

Interior
National Park Service
NER SERVICES MABO (43000)
BOSTON, MA, 02108, United States

Place of Performance

Charlestown, MA

NAICS

Other Heavy and Civil Engineering Construction (237990)

PSC

Maintenance Of Other Non Building Facilities (Z1PZ)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Jan 26, 2026
2
Last Updated
Feb 27, 2026
3
Submission Deadline
Feb 26, 2026, 6:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The National Park Service (NPS), Northeast Region, has issued a Request for Proposal (RFP) for the A250 Emergency Repairs to Pier 1 located within the Charlestown Navy Yard at Boston National Historic Park, MA. This project addresses critical structural repairs to the pier and associated maritime infrastructure. This is a Total Small Business Set-Aside with an estimated magnitude between $1,000,000 and $5,000,000. Proposals are due February 26, 2026.

Scope of Work

The contractor will provide all labor, materials, and equipment for:

  • Repairing concrete-encased steel beams within three pier vaults.
  • Remediating sinkholes on the topside of the pier deck.
  • Repairing concrete delamination on the pier underdeck.
  • Structural repairs to an existing steel barge.
  • Repairing the connection between an aluminum gangway and the concrete deck platform.
  • Maintaining continuous pier operations for NPS and Navy use during construction.

Contract & Timeline

  • Type: Firm-Fixed Price (FFP)
  • Set-Aside: Total Small Business
  • Period of Performance: Work must commence within 14 days of Notice to Proceed and be completed within 87 calendar days.
  • Site Visit: February 12, 2026, at 11:00 AM EST at the USS Constitution Museum.
  • Response Due: February 26, 2026, at 11:00 AM EST.

Evaluation

Selection will be based on a Best Value Tradeoff Process. Evaluation factors include:

  1. Technical Approach
  2. Project Experience
  3. Management Experience
  4. Price Non-price factors are of equal importance and, when combined, are approximately equal to price.

Additional Notes

Offerors must provide a bid guarantee of 20% of the bid price or $3 million (whichever is less). Performance and Payment Bonds (100%) are required upon award. Site access requires a TWIC card, and contractors must comply with Davis-Bacon wage determinations for Suffolk County, MA.

People

Points of Contact

Tolleson, MariPRIMARY

Files

Files

Download

Versions

Version 5
Solicitation
Posted: Feb 27, 2026
View
Version 4
Solicitation
Posted: Feb 24, 2026
View
Version 3
Solicitation
Posted: Feb 23, 2026
View
Version 2Viewing
Solicitation
Posted: Feb 9, 2026
Version 1
Pre-Solicitation
Posted: Jan 26, 2026
View