Z--CT SWITCHGEAR REPLACEMENT STAMPEDE PP

SOL #: 140R2026R0007Solicitation

Overview

Buyer

Interior
Bureau Of Reclamation
MP-REGIONAL OFFICE
SACRAMENTO, CA, 95825, United States

Place of Performance

Place of performance not available

NAICS

Electrical Contractors and Other Wiring Installation Contractors (238210)

PSC

Repair Or Alteration Of Epg Facilities Other, Including Transmission (Z2MZ)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Mar 20, 2026
2
Last Updated
Jun 18, 2026
3
Submission Deadline
Jun 28, 2026, 12:00 AM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Bureau of Reclamation is soliciting proposals for a firm, fixed-price construction contract for the Stampede Power Plant Switchgear Replacement project in Truckee, CA. This project involves replacing outdated electrical switchgear and distribution panels with new arc-resistant systems. The procurement is a Total Small Business Set-Aside. Proposals are due June 27, 2026, at 1700 PDT.

Scope of Work

The project requires the removal and replacement of existing electrical components, including:

  • DCA Switchgear: Removal of the 480-Volt feeder enclosure and five (5) breakers, and installation of a new arc-resistant enclosure with five (5) new arc-limiting 480-Volt draw-out circuit breakers and one (1) spare breaker.
  • DCB Enclosure: Removal and replacement of the existing DCB enclosure and integrated molded case circuit breaker distribution panel.
  • D1A and DCC Panels: Removal and replacement of existing molded case circuit breaker distribution panels.
  • The contractor must provide backup generator power, restroom facilities, and hand wash stations.
  • Work requires adherence to electrical safety, arc flash mitigation, quality control, and applicable codes. Offerors must submit valid business licenses for electrical construction.

Contract Details

  • Solicitation Number: 140R2026R0007
  • Contract Type: Firm-Fixed Price
  • Estimated Value: $250,000.00 to $500,000.00
  • Period of Performance: Commence within 7 calendar days after award, complete within 150 calendar days after Notice to Proceed.
  • Set-Aside: Total Small Business (FAR 19.5)
  • NAICS Code: 238210 (Small Business Size Standard: $19M)
  • Bonds: 100% Performance and Payment Bonds are required within 10 calendar days after award.

Submission & Evaluation

  • Proposal Due Date: June 27, 2026, at 1700 local time (PDT).
  • Submission: Sealed offers must be marked with offeror's name, address, solicitation number, and due date/time.
  • Procurement Method: FAR Part 15, Contracting by Negotiation.
  • Evaluation Factors: Award will be based on the lowest evaluated price among proposals meeting or exceeding acceptability standards for non-cost/price factors. Evaluation includes Technical Capability (Technical Approach, Construction Schedule, Experience) and Past Performance, with no trade-offs.
  • Site Visit: An organized site visit was scheduled for June 9, 2026, at 10:00 AM PST. An amendment incorporates the site visit agenda and sign-in sheet.
  • Questions Deadline: Five (5) days after the site visit at 1700 PST.
  • Registration: Offerors must be actively registered in SAM.gov.
  • Drawings/SOW: Requires execution of a Non-Disclosure Agreement (NDA) to access drawings and the Statement of Work.

Contact Information

People

Points of Contact

Ahola, RoxanaPRIMARY

Files

Files

Download
Download
Download
Download
Download

Versions

Version 6
Solicitation
Posted: Jun 18, 2026
View
Version 5Viewing
Solicitation
Posted: Jun 11, 2026
Version 4
Solicitation
Posted: May 28, 2026
View
Version 3
Pre-Solicitation
Posted: Apr 30, 2026
View
Version 2
Sources Sought
Posted: Apr 8, 2026
View
Version 1
Sources Sought
Posted: Mar 20, 2026
View