CUSTER GALLATION NATIONAL FOREST - Riley Pass Bluff B Mine Waste Excavation Project
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The USDA Forest Service, Custer Gallatin National Forest, has issued a Request for Quotation (RFQ) for the Riley Pass Bluff B Mine Waste Excavation Project in Harding County, South Dakota. This project involves excavating and consolidating historic mine waste. This opportunity is a 100% Small Business Set-Aside. Quotes are due by March 3, 2026, at 4:00 PM Mountain Time.
Scope of Work
This project requires the excavation of historic mine waste at various locations on Bluff B, followed by its placement and compaction into designated consolidation areas. Key tasks include site preparation, grading, construction of roadways and embankments, dust control, erosion control, turf establishment, and aggregate course placement. Mine waste is specifically defined by arsenic and radium-226 concentrations. GPS-controlled equipment is required for excavation and consolidation.
Key Requirements
- Documents to Return: Schedule of Items, a document demonstrating recent and relevant experience and past performance (limited to a 10-page narrative), a bid guarantee (if applicable), and acknowledgment of any amendments.
- Bonds: A 20% bid bond/offer guarantee is required if the quote exceeds $150,000. Performance and Payment Bonds, each at 100% of the original contract price, are required for contracts over $150,000, due 10 days post-award. For contracts between $35,000 and $150,000, payment protections (irrevocable letter of credit or payment bond) are required within 10 days of award.
- Working Hours: Work is generally restricted from weekends and holidays unless approved by the Contracting Officer; night work is not permitted.
- Completion Dates: All non-seeding work must be completed by July 1, 2026. Seeding must occur by June 15, 2026, or between September 15 and October 15, 2026. The period of performance will not be extended.
- Site Conditions: The work area includes slopes up to 70%. Site access during the advertisement period is by walking in; keys will be provided post-award. Visuals of the site are available in Attachment 6, Site Photos. The initial 85,000 CY of excavation must be completed first.
- Wage Rates: Prevailing wage rates for South Dakota Heavy and Highway Construction Projects, as per the Davis-Bacon Act, apply.
Contract Details
- Type: Firm Fixed-Price Request for Quotation (RFQ).
- NAICS: 562910 (Remediation Services), with a size standard of 1,000 employees.
- Set-Aside: 100% Small Business.
- Place of Performance: North Cave Hills land unit of the Custer-Gallatin National Forest, Harding County, South Dakota.
Submission & Evaluation
- Quote Due: March 3, 2026, 4:00 PM Mountain Time.
- Questions Due: February 23, 2026, 12:00 PM Mountain Time.
- Submission: Quotes and questions should be emailed to Alisha Knaub at alisha.knaub@usda.gov.
- Evaluation: Award will be based on the best value to the Government, considering Experience and Past Performance, evaluated for relevancy, size, complexity, type of work, recency, and quality. A comparative methodology will be used.
Amendments
Amendment 001, posted February 11, 2026, added site photos (Attachment 6), clarified that 85,000 CY of excavation shall be completed first, and specified a 10-page limit for the narrative response. It also confirmed working hour restrictions.