CUSTER GALLATIN NATIONAL FOREST - Riley Pass Bluff B Mine Waste Excavation Project
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The USDA Forest Service, Custer Gallatin National Forest is soliciting quotes for the Riley Pass Bluff B Mine Waste Excavation Project in Harding County, South Dakota. This Total Small Business Set-Aside opportunity involves excavating and consolidating historic mine waste. Quotes are due March 3, 2026, at 4:00 PM Mountain Time.
Project Scope
This project requires the excavation of historic mine waste at various locations on Bluff B and its placement and compaction into designated consolidation areas. Key tasks include:
- Site preparation, grading, and construction of roadways.
- Implementation of erosion control measures and dust suppression.
- Turf establishment using Sterile Rye seeding.
- Placement of aggregate courses.
- Mine waste excavation requires GPS-controlled equipment.
- Personnel must have OSHA 40-hour HAZWOPER training.
- The project site features steep slopes (up to 70%), requiring a submitted haul plan and ingress/egress from the bluff top.
Contract Details
- Contract Type: Firm-Fixed-Price Request for Quotation (RFQ).
- NAICS Code: 562910 (Remediation Services), Size Standard: 1,000 employees.
- Set-Aside: Total Small Business.
- Period of Performance: Non-seeding work must be completed by July 1, 2026. Seeding must occur by June 15, 2026, or between September 15 – October 15, 2026. No extensions will be granted.
- Bonds: A 20% bid guarantee is required for quotes exceeding $150,000. Performance and Payment Bonds (100% of contract price) are required for contracts over $150,000, due 10 days post-award. Payment protections are required for contracts between $35,000 and $150,000.
- Wage Rates: Davis-Bacon Act prevailing wage rates for South Dakota Heavy and Highway Construction apply.
Submission Requirements & Evaluation
Quoters must submit:
- A completed Schedule of Items with pricing.
- A document demonstrating recent and relevant experience and past performance (narrative limited to 10 pages).
- A bid guarantee (if applicable).
- Acknowledgment of all amendments. Evaluation will be based on Best Value to the Government, considering the relevancy, size, complexity, type of work, recency, and quality of experience and past performance.
Key Dates & Contact
- Questions Due: February 23, 2026, 12:00 PM Mountain Time.
- Quotes Due: March 3, 2026, 4:00 PM Mountain Time.
- Contact: Alisha Knaub, alisha.knaub@usda.gov, (406)438-2981.
Amendments & Clarifications
Amendment 001 (Feb 11, 2026) added site photos and clarified excavation quantities, narrative page limits, and working hour restrictions. The latest Q&A (Feb 18, 2026) further confirmed these details, including firm completion dates and site access protocols. Work is generally restricted to weekdays, with no night work.